Permit 202307132080

333 Post St

installation of temporary ice rink, ticket booth, skate booth, canopies, lighting for evening skating.

Outcome
Completed (city status: complete, Jan 23, 2024)
Filed
Jul 13, 2023
Permit issued
Jul 14, 2023
Final sign-off
Jan 23, 2024
Declared cost
$150,000
Building use
public assmbly other
Neighborhood
Financial District/South Beach (how long permits take there)
Contractor
Owner-builder: the owner is listed as the builder, so no contractor is ranked for this permit
Property
All permits at this address (block 0308, lot 001)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Owner-builder
Owner Builder
Authorized agent
Matt Kessinger (no license listed), applicant