Permit 202109279192
425 Holly Park Cr
revision to bpa#201612155093 to repair rear extension only, footings, repair deteriorated framing, remove/rebuild (1) exterior stair in-kind, new 1-hour rated property line wall & guard.
- Outcome
- Completed (city status: complete, Dec 12, 2023)
- Filed
- Sep 27, 2021
- Permit issued
- Oct 5, 2021
- Final sign-off
- Dec 12, 2023
- Declared cost
- $50,000
- Building use
- 2 family dwelling
- Neighborhood
- Bernal Heights
- Contractor
- The Sustainable Cbo Inc Dba Oliver Macki (license 988725)
- Project type
- Stairs
- Property
- All permits at this address (block 5721, lot 044)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- The Sustainable Cbo Inc Dba Oliver Macki (license 988725)
- Architect
- Edward Lee Hammack, Edw. Lee Hammack, Architect (license C13890), applicant