Permit 201912038488
100 Pine St
ti for partial e office, includes new conf rm relocate break rm, relaxation room, new partitions deferred mep and fire protection, maher not req
- Outcome
- Completed (city status: complete, May 22, 2020)
- Filed
- Dec 3, 2019
- Permit issued
- Dec 4, 2019
- Final sign-off
- May 22, 2020
- Declared cost
- $646,014
- Building use
- office
- Neighborhood
- Financial District/South Beach (how long permits take there)
- Contractor
- Team Commercial Construction Inc. (license 735561)
- Property
- All permits at this address (block 0262, lot 020)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- Team Commercial Construction Inc. (license 735561)
- Architect
- Donnie Lam, Interior Architects (license C32542)