Permit 201907317517
1515 03rd St
structural, mechanical, ele, plumbing engineering and deisign for a complete and operational fuel cell system that will serve future telecommunications and network rooms in building. tlecommunications and network rooms under ti maher not req
- Outcome
- Never finaled (city status: issued, Dec 3, 2019)
- Filed
- Jul 31, 2019
- Permit issued
- Dec 3, 2019
- Declared cost
- $75,000
- Building use
- office
- Neighborhood
- Mission Bay (how long permits take there)
- Contractor
- Truebeck Construction (license 903798)
- Property
- All permits at this address (block 8721, lot 029)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- Truebeck Construction (license 903798), applicant
- Engineer
- Fini Jafar (license 12691)