Permit GraphShortlistSan Francisco building permits since 2000

Permit 201902263857

601 22nd St

interior work to add ramp to loading dock to existing manufacturing space. new storefront beyond facade. new roll up door. new accessible restroom. floor level change and minimal foundation work. removal of curbcut on 22nd st/illinois.

Outcome
Completed (city status: complete, Dec 20, 2021)
Filed
Feb 26, 2019
Permit issued
May 13, 2019
Final sign-off
Dec 20, 2021
Declared cost
$240,000
Building use
retail sales
Neighborhood
Potrero Hill (how long permits take there)
Contractor
Dajani Construction (license 685647)
Property
All permits at this address (block 4173, lot 001)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Contractor
Dajani Construction (license 685647), applicant
Engineer
Leandre Davis, Takami Engineering (no license listed)