Permit GraphShortlistSan Francisco building permits since 2000

Permit 201901150460

150 Green St

penthouse b: barrier removal, new ada restroom, and new kitchenette. n/a for maher

Outcome
Completed (city status: complete, May 29, 2019)
Filed
Jan 15, 2019
Permit issued
Feb 6, 2019
Final sign-off
May 29, 2019
Declared cost
$50,000
Building use
office
Neighborhood
Financial District/South Beach (how long permits take there)
Contractor
Owner-builder: the owner is listed as the builder, so no contractor is ranked for this permit
Project type
Kitchen remodel
Property
All permits at this address (block 0112, lot 008)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Owner-builder
Owner Builder
Architect
Ryan Barr (license C33495)
Pmt consultant/expediter
Kyle Thompson, A. R. Sanchez (no license listed), applicant