Permit 201812188582
225 Bush St
3rd flr non structural demo (n) toilet room build back for accesibility mep, life safety, sprinklers under separate permit no change in occupancy, use or area
- Outcome
- Completed (city status: complete, May 16, 2019)
- Filed
- Dec 18, 2018
- Permit issued
- Dec 19, 2018
- Final sign-off
- May 16, 2019
- Declared cost
- $150,000
- Building use
- office
- Neighborhood
- Financial District/South Beach (how long permits take there)
- Contractor
- Field Construction Inc. (license 306094)
- Property
- All permits at this address (block 0289, lot 001)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- Field Construction Inc. (license 306094)
- Architect
- George Soskin, Huntsman (license C9223)