Permit GraphShortlistSan Francisco building permits since 2000

Permit 201812067589

150 Spear St

revision to pa #201803294961. added 02/c02 sensor with strobe per sffd comments during final medigas inspection. location is medical gas storage room 573.

Outcome
Completed (city status: complete, Jun 4, 2019)
Filed
Dec 6, 2018
Permit issued
Dec 6, 2018
Final sign-off
Jun 4, 2019
Declared cost
$3,000
Building use
office
Neighborhood
Financial District/South Beach (how long permits take there)
Contractor
Truebeck Construction (license 903798)
Property
All permits at this address (block 3717, lot 021)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Contractor
Truebeck Construction (license 903798)
Engineer
Tom Gajek, Acies Engineering (license C15130)