Permit 201810163250
555 San Jose Av
new concrete pads for pge transformer to tie into untilities and new switchboard. utilities trench up san jose ave for future tie in to hartzell distribution panel
- Outcome
- Completed (city status: complete, Dec 28, 2020)
- Filed
- Oct 16, 2018
- Permit issued
- Feb 20, 2019
- Final sign-off
- Dec 28, 2020
- Building use
- clinics-medic/dental
- Neighborhood
- Bernal Heights (how long permits take there)
- Contractor
- Rudolph And Sletten Inc (license 198069)
- Property
- All permits at this address (block 6575, lot 005)