333 Bush St
project consist of remaning interconnection, non-egress stair enclosure on fl. 31 and infilling slab. demolition of exisitng dead end stringer going up to fl 32. new partitions and doors to be built on 30th fl. landing to block access to dead end stairs. stair is not used for egress no new pp, ep,
- Outcome
- Never finaled (city status: issued, Oct 9, 2018)
- Filed
- Aug 21, 2018
- Permit issued
- Oct 9, 2018
- Declared cost
- $10,000
- Building use
- office
- Neighborhood
- Financial District/South Beach (how long permits take there)
- Contractor
- None listed with a license number
- Project type
- Stairs
- Property
- All permits at this address (block 0288, lot 032)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.