Permit 201807174756
200 Paul Av
new data center on third floor of (e) bldg. (n) walls, doors, finishes, and (n) mechanical, eletrical work. (n) condensors and air handling unit on roof
- Outcome
- Never finaled (city status: issued, Nov 8, 2018)
- Filed
- Jul 17, 2018
- Permit issued
- Nov 8, 2018
- Declared cost
- $6,250,000
- Building use
- office
- Neighborhood
- Bayview Hunters Point
- Contractor
- Dpr Construction (license 953749)
- Property
- All permits at this address (block 5431A, lot 001G)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- Dpr Construction (license 953749)
- Architect
- Randall Dowler, Dowler Gruman Architects (license C23107)
- Pmt consultant/expediter
- Carlos Blanco (no license listed), applicant