Permit 201805078353
300 Clay St
an existing 1750 sf space in the basement of a high rise office building is to be converted from storage to a corporate workout facility. work will include general fitness as well sa mech, elec., ams, and plumbing.
- Outcome
- Completed (city status: complete, May 31, 2019)
- Filed
- May 7, 2018
- Permit issued
- May 9, 2018
- Final sign-off
- May 31, 2019
- Declared cost
- $1,200,000
- Building use
- office
- Neighborhood
- Financial District/South Beach
- Contractor
- Plant Construction Co, Lp (license 995375)
- Property
- All permits at this address (block 0204, lot 021)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- Plant Construction Co, Lp (license 995375)
- Architect
- Mark Horton, Mark Horton Architecture (license C018065), applicant
- Lessee
- Farallon (no license listed)