Permit 201803305182
580 Noe St
add units per ordinance 162-16. add (3) accessory dwelling units to the walk-out basement level of an existing 2-story 8 unit building, all work within existing building envelope.
- Outcome
- Completed (city status: complete, Dec 5, 2022)
- Filed
- Mar 30, 2018
- Permit issued
- Jul 15, 2019
- Final sign-off
- Dec 5, 2022
- Declared cost
- $175,000
- Building use
- apartments
- Neighborhood
- Castro/Upper Market
- Contractor
- Owner-builder: the owner is listed as the builder, so no contractor is ranked for this permit
- Property
- All permits at this address (block 3583, lot 016)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Owner-builder
- Owner Builder
- Architect
- Gary Meyer, Wayne Myer Works Arch (license C31705)
- Engineer
- Engin Yagmur, Ecr Engineering (license C76016)