Permit GraphShortlistSan Francisco building permits since 2000

Permit 201803073071

100 California St

revision to app#201612225779 and app 201602129534 to change proposed design elements and materials on 14th and 15th floor. add a new 2-stage elevator, no work on existing elevator lobby doors. fire and mep under separate permits. n/a for maher

Outcome
Completed (city status: complete, Jun 4, 2019)
Filed
Mar 7, 2018
Permit issued
Mar 8, 2018
Final sign-off
Jun 4, 2019
Declared cost
$110,000
Building use
office
Neighborhood
Financial District/South Beach (how long permits take there)
Contractor
Principal Builders Inc. (license 829808)
Property
All permits at this address (block 0236, lot 017)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Contractor
Principal Builders Inc. (license 829808)