Permit GraphShortlistSan Francisco building permits since 2000

Permit 201802131135

200 Paul Av

provide pre-action detection & controls for 3rd flr suite# 350 data center & elect rms.

Outcome
Completed (city status: complete, May 17, 2018)
Filed
Feb 13, 2018
Permit issued
Mar 9, 2018
Final sign-off
May 17, 2018
Declared cost
$22,280
Building use
office
Neighborhood
Bayview Hunters Point (how long permits take there)
Contractor
Intelligent Technologies & Services Inc (license 592289)
Property
All permits at this address (block 5431A, lot 001F)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Contractor
Intelligent Technologies & Services Inc (license 592289)