Permit 201711164136
121 Spear St
5th floor: level 5: coffee barista, counter, general seating . level 2 catering pantry. mep included. n/a for maher.
- Outcome
- Completed (city status: complete, Jun 25, 2019)
- Filed
- Nov 16, 2017
- Permit issued
- Dec 8, 2017
- Final sign-off
- Jun 25, 2019
- Declared cost
- $950,000
- Building use
- office
- Neighborhood
- Financial District/South Beach (how long permits take there)
- Contractor
- Bcci Construction Company (license 492944)
- Property
- All permits at this address (block 3716, lot 021)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- Bcci Construction Company (license 492944)