Permit GraphShortlistSan Francisco building permits since 2000

Permit 201709279652

275 Battery St

non-struct demo (n) non-struct partitions, finishes, doors, glazing, lighting. no change in occupancy, use or area. mep deferred submittal

Outcome
Completed (city status: complete, Dec 19, 2017)
Filed
Sep 27, 2017
Permit issued
Sep 28, 2017
Final sign-off
Dec 19, 2017
Declared cost
$188,994
Building use
office
Neighborhood
Financial District/South Beach (how long permits take there)
Contractor
Skyline Construction (license 727637)
Property
All permits at this address (block 0238, lot 001)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Contractor
Skyline Construction (license 727637)
Architect
George Soskin, Huntsman (license C9223)