Permit GraphShortlistSan Francisco building permits since 2000

Permit 201708154831

30 Crestline Dr

compliance with mandatory seismic retofit program per 2016 sfebc chapter 4d & 2016 cebc appx a4.

Outcome
Completed (city status: complete, Dec 28, 2018)
Filed
Aug 15, 2017
Permit issued
Dec 18, 2017
Final sign-off
Dec 28, 2018
Declared cost
$60,000
Building use
apartments
Neighborhood
Twin Peaks
Contractor
Owner-builder: the owner is listed as the builder, so no contractor is ranked for this permit
Property
All permits at this address (block 2845, lot 011)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Owner-builder
Owner Builder
Engineer
Donald David, Double D Engineering (license S3928)
Authorized agent-others
Brendan Davidson, Double D Engineering (no license listed)