Permit 201708084127
215 Fremont St
on 6th floor - add 12 new strobes, 2 speaker strobes 3 sync modules while relocating 38 (e) speaker strobes fit bit suite
- Outcome
- Completed (city status: complete, Dec 8, 2017)
- Filed
- Aug 8, 2017
- Permit issued
- Aug 8, 2017
- Final sign-off
- Dec 8, 2017
- Declared cost
- $10,000
- Building use
- office
- Neighborhood
- Financial District/South Beach
- Contractor
- Tri-Signal Integration Inc. (license 758792)
- Property
- All permits at this address (block 3738, lot 012)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- Tri-Signal Integration Inc. (license 758792), applicant