Permit 201603182499
450 Sutter St
8th flr: new interior ti including demising walls and new finishes in (e) suite and expansion into adjacent suite. ele/plumb/fire/life safety undersep permit. maher na
- Outcome
- Completed (city status: complete, May 24, 2017)
- Filed
- Mar 18, 2016
- Permit issued
- Mar 31, 2016
- Final sign-off
- May 24, 2017
- Declared cost
- $45,392
- Building use
- office
- Neighborhood
- Financial District/South Beach (how long permits take there)
- Contractor
- Derry Casey Builders (license 789691)
- Property
- All permits at this address (block 0285, lot 006)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- Derry Casey Builders (license 789691)
- Pmt consultant/expediter
- Kyle Sheehy (no license listed), applicant