Permit 201511132553

150 California St

18th floor: mechanical work-modification of (e) hvac systems-addition of vav box w/controls air balance. building pa 2015-1002-8676. maher na

Outcome
Completed (city status: complete, Apr 22, 2016)
Filed
Nov 13, 2015
Permit issued
Nov 16, 2015
Final sign-off
Apr 22, 2016
Declared cost
$12,000
Building use
office
Neighborhood
Financial District/South Beach (how long permits take there)
Contractor
Richlen Construction (license 570031)
Property
All permits at this address (block 0236, lot 019)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Contractor
Richlen Construction (license 570031), applicant