Permit 201508033172
995 Pine St
soft story retrofit per sfbc chapter 34b "2012 iebc appendix a-4." comliance with mandatory soft story retrofit program, iebc sec a4.
- Outcome
- Completed (city status: complete, Nov 15, 2016)
- Filed
- Aug 3, 2015
- Permit issued
- May 4, 2016
- Final sign-off
- Nov 15, 2016
- Declared cost
- $40,000
- Building use
- apartments
- Neighborhood
- Nob Hill (how long permits take there)
- Contractor
- Sure, Inc. (license 561658)
- Property
- All permits at this address (block 0274, lot 016)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- Sure, Inc. (license 561658)
- Engineer
- Donald David, Double D Engineering (license S3928)
- Authorized agent
- Victor Leao-David, Double D Engineers (no license listed), applicant