Permit GraphShortlistSan Francisco building permits since 2000

Permit 201310229895

150 Spear St

3rd floor-add & relocate fire sprinklers per t.i-add 3 & relocate 32

Outcome
Completed (city status: complete, Nov 25, 2013)
Filed
Oct 22, 2013
Permit issued
Oct 22, 2013
Final sign-off
Nov 25, 2013
Declared cost
$18,000
Building use
office
Neighborhood
Financial District/South Beach (how long permits take there)
Contractor
Ayoob & Peery Plumbing Co Inc (license 392967)
Property
All permits at this address (block 3717, lot 021)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Contractor
Ayoob & Peery Plumbing Co Inc (license 392967), applicant