Permit 201310088730
1001 Potrero Av
mayor's office on disability ada barrier removal project per cbc work involves renovating a primary entrance to sfgh building 9 for accessibility compliance including new ramps, stairs & landscaping.
- Outcome
- Completed (city status: complete, Oct 29, 2015)
- Filed
- Oct 8, 2013
- Permit issued
- Dec 30, 2013
- Final sign-off
- Oct 29, 2015
- Declared cost
- $275,000
- Building use
- hospital
- Neighborhood
- Mission (how long permits take there)
- Contractor
- Owner-builder: the owner is listed as the builder, so no contractor is ranked for this permit
- Project type
- Stairs
- Property
- All permits at this address (block 4154, lot 001)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Owner-builder
- Owner Builder
- Architect
- Marilyn Thompson, Ccsf (license C18884), applicant