Permit 201210091513
188 Spear St
3rd floor:fire sprinkler system upgrade. relocate 83 pendent sprinkler heads on the 3rd floor. relocate 88 upright heads. app#201208167530
- Outcome
- Completed (city status: complete, Feb 26, 2013)
- Filed
- Oct 9, 2012
- Permit issued
- Oct 10, 2012
- Final sign-off
- Feb 26, 2013
- Declared cost
- $88,065
- Building use
- office
- Neighborhood
- Financial District/South Beach (how long permits take there)
- Contractor
- Golden Gate Fire Protection Inc (license 960198)
- Property
- All permits at this address (block 3717, lot 019)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- Golden Gate Fire Protection Inc (license 960198), applicant