revision to approved appl. 2008 0930 3040: final plans for site improvements and underground utilities associated with the transbay cable project. landscaping work to be submitted under a separate permit.
- Outcome
- Completed (city status: complete, Jan 19, 2010)
- Filed
- Oct 24, 2008
- Permit issued
- Nov 12, 2008
- Final sign-off
- Jan 19, 2010
- Building use
- power plant
- Neighborhood
- Potrero Hill
- Contractor
- None listed with a license number
- Property
- All permits at this address (block 4232, lot 010)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Authorized agent-others
- Siemens (no license listed)