- 14 permits filed
24 permits since 2000: 20 completed, 4 in progress.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Dec 22, 2025 | In progress issued Dec 2025 | 2000 Marin St | requesting to have approval for temporary stand pipe for existing fire hydrant locations admin building. per cfc 3314Details
requesting to have approval for temporary stand pipe for existing fire hydrant locations admin building. per cfc 3314 | |
| Oct 23, 2025 | Completed final sign-off Oct 2025 | 3251 20th Av | as built (no fire sprinkler work) no hangers (plumbing) work ref pa 202509296158Details
as built (no fire sprinkler work) no hangers (plumbing) work ref pa 202509296158 | |
| Sep 26, 2025 | Completed final sign-off Oct 2025 | 3251 20th Av | suite 203: relocating 5 sprinkler heads and adding 1 sprinkler head for the area of work. ref ti permit 202505227057Details
suite 203: relocating 5 sprinkler heads and adding 1 sprinkler head for the area of work. ref ti permit 202505227057 | $12,050 |
| Aug 29, 2025 | In progress issued Aug 2025 | 3251 20th Av | suite 167a, relocate 14 and add 4 fire sprinklers fornew store layout. seismic upgrade to existing pipe in area of work only. bldg ref#: 202506138697.Details
suite 167a, relocate 14 and add 4 fire sprinklers fornew store layout. seismic upgrade to existing pipe in area of work only. bldg ref#: 202506138697. | $26,775 |
| Aug 29, 2025 | In progress issued Aug 2025 | 3251 20th Av | suite 250. relocate 9 sprinkler heads for new suite layout. seismic upgrade to existing pipes in area of work only. ref#: 202501218731Details
suite 250. relocate 9 sprinkler heads for new suite layout. seismic upgrade to existing pipes in area of work only. ref#: 202501218731 | $12,150 |
| Aug 13, 2025 | Completed final sign-off May 2026 | 3251 20th Av | relocate 10 and add 2 fire sprikler heads for the (n) store layout. seismic upgrade for (e) pipe area of work onlyDetails
relocate 10 and add 2 fire sprikler heads for the (n) store layout. seismic upgrade for (e) pipe area of work only | $13,950 |
| Jun 6, 2025 | Completed final sign-off Sep 2025 | 3251 20th Av | space 175 ref pa # 202504083935: relocate 1 and add 17 fire sprinkler heads for new store layout. seismic upgrade to existing sprinkler system in area of work only.Details
space 175 ref pa # 202504083935: relocate 1 and add 17 fire sprinkler heads for new store layout. seismic upgrade to existing sprinkler system in area of work only. | $19,125 |
| May 23, 2025 | Completed final sign-off Jul 2025 | 3251 20th Av | space/345: add 31 and relocate 9 fire sprinkler heads for new store layout. seismic upgrade to main and branch lines in area of the work only.Details
space/345: add 31 and relocate 9 fire sprinkler heads for new store layout. seismic upgrade to main and branch lines in area of the work only. | $29,677 |
| May 14, 2025 | Completed final sign-off Jul 2025 | 3251 20th Av | suite 172 ref pa #2024-1002-2121 add 5 and relocate 6 fire sprinkler heads for new restaurant layoutDetails
suite 172 ref pa #2024-1002-2121 add 5 and relocate 6 fire sprinkler heads for new restaurant layout | $16,807 |
| May 8, 2025 | In progress filed May 2025, not yet issued | 475 28th St | installation of fire sprinkler system ref 202107154487Details
installation of fire sprinkler system ref 202107154487 | $23,000 |
| Mar 25, 2025 | Completed final sign-off Apr 2025 | 3251 20th Av | relocate 1 pendent. add 1 new pendant for new tenant layout.Details
relocate 1 pendent. add 1 new pendant for new tenant layout. | $8,775 |
| Jan 29, 2025 | Completed final sign-off May 2025 | 555 Fulton St | modify 8 sprinkler heads ref 202310249379Details
modify 8 sprinkler heads ref 202310249379 | $14,535 |
| Jan 15, 2025 | Completed final sign-off Apr 2025 | 400 Winston Dr | add 14 and relocate 4 fire sprinklers for new walls and ceilings bldg pa# 202410293998Details
add 14 and relocate 4 fire sprinklers for new walls and ceilings bldg pa# 202410293998 | $18,765 |
| Oct 30, 2024 | Completed final sign-off May 2025 | 3251 20th Av | #219a: modify 19 fire sprinkler heads for new restaurant layout, hanger and seismic bracing upgrades to existing pipe in area of work only. ref bldg pa #202406124283.Details
#219a: modify 19 fire sprinkler heads for new restaurant layout, hanger and seismic bracing upgrades to existing pipe in area of work only. ref bldg pa #202406124283. | $23,985 |
| Jul 24, 2024 | Completed final sign-off Feb 2025 | 3251 20th Av | as built drawings for permit 202405293139 for fire sprinkler systemDetails
as built drawings for permit 202405293139 for fire sprinkler system | |
| Jun 7, 2024 | Completed final sign-off Feb 2025 | 3251 20th Av | ref pa# 2024-0118-4225 ste #221 modifying 19 sprinklers for new store layoutDetails
ref pa# 2024-0118-4225 ste #221 modifying 19 sprinklers for new store layout | $19,575 |
| May 29, 2024 | Completed final sign-off Jul 2024 | 3251 20th Av | suite 103-fire only- modify (3) sprinkers for (n) store layoutDetails
suite 103-fire only- modify (3) sprinkers for (n) store layout | $9,837 |
| May 23, 2024 | Completed final sign-off Jul 2024 | 3251 20th Av | modifying 17 sprinkler heads for new retail remodelDetails
modifying 17 sprinkler heads for new retail remodel | $10,000 |
| Apr 24, 2024 | Completed final sign-off May 2024 | 611 Folsom St | remove one wall mounted fire department connection to new location outside of gated entry. install new fire department connection.Details
remove one wall mounted fire department connection to new location outside of gated entry. install new fire department connection. | $7,950 |
| Oct 12, 2023 | Completed final sign-off Feb 2025 | 156 Lunado Ct | revision to 202307283227 for fire sprinklers. cpvc to copper.Details
revision to 202307283227 for fire sprinklers. cpvc to copper. | |
| Jul 28, 2023 | Completed final sign-off Apr 2026 | 156 Lunado Ct | installation of fire sprinkler systemDetails
installation of fire sprinkler system | $32,600 |
| Jul 6, 2023 | Completed final sign-off Jun 2024 | 40 Montclair Tr | as built #202304045041, after passed rough hydro/ glue inspection- added sprinkler heads to 2nd flr per inspector.Details
as built #202304045041, after passed rough hydro/ glue inspection- added sprinkler heads to 2nd flr per inspector. | $32,600 |
| Apr 4, 2023 | Completed final sign-off Mar 2024 | 40 Montclair Tr | revision to previously approved pa# 202203240753: to change location of riser & backflow type per puc/water. fdc to remain.Details
revision to previously approved pa# 202203240753: to change location of riser & backflow type per puc/water. fdc to remain. | |
| Mar 24, 2022 | Completed final sign-off Feb 2024 | 40 Montclair Tr | installation of fire sprinkler system. ref permit 201610200800.Details
installation of fire sprinkler system. ref permit 201610200800. | $32,600 |