- Aug 2000 to Apr 2015
- Last 24 months
- 0 permits filed
36 permits since 2000: 31 completed, 3 never finaled, 2 expired or cancelled.
Of the 3 never-finaled permits, 3 are over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for kitchen remodel across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Kitchen remodel permits
8 kitchen remodel permits: 7 completed, 1 never finaled. Typically 0 days from filing to permit and 43 days from permit to final inspection.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Aug 20, 2013 | Completed final sign-off Oct 2013 | 255 Arkansas St | unit #255: comply with physical inspection report cc-7239; stair rails, dryer vent and kitchen; remodel (no structural) onlyDetails
unit #255: comply with physical inspection report cc-7239; stair rails, dryer vent and kitchen; remodel (no structural) only | $5,000 |
| Apr 10, 2012 | Completed final sign-off May 2012 | 55 Exeter St | demo kitchen cabinets/plaster, change galv. piping to copper, new circuits as required, insulate walls sheetrock, 5/8" gyp. board, new cabinet, new dishwasher, new lighting per cec150(k), no structural work.Details
demo kitchen cabinets/plaster, change galv. piping to copper, new circuits as required, insulate walls sheetrock, 5/8" gyp. board, new cabinet, new dishwasher, new lighting per cec150(k), no structural work. | $12,000 |
| May 12, 2010 | Completed final sign-off Jun 2010 | 3223 Folsom St | replace kitchen & bathroom in unit "b" first floor.Details
replace kitchen & bathroom in unit "b" first floor. | $15,000 |
| Mar 22, 2010 | Completed final sign-off May 2010 | 3223 Folsom St | unit #3223 - replace kitchen & bathroom fistures, wall repair, paint, new tile flooring, no structural work.Details
unit #3223 - replace kitchen & bathroom fistures, wall repair, paint, new tile flooring, no structural work. | $10,000 |
| Aug 27, 2009 | Completed final sign-off Nov 2009 | 167 08th Av | kitchen & bathroom remodl. no structural cabinets & counters. nothing relocated.Details
kitchen & bathroom remodl. no structural cabinets & counters. nothing relocated. | $18,000 |
| Mar 4, 2009 | Completed final sign-off Oct 2009 | 3431 Mission St | comply with 3r4844, revert space back to original use. remove residential components: kitchen, laundry, dark rm.Details
comply with 3r4844, revert space back to original use. remove residential components: kitchen, laundry, dark rm. | $40,000 |
| Mar 30, 2007 | Completed final sign-off May 2007 | 743 Arguello Bl | change kitchen counter/ba vinets, bath lav/vanity work in unit #3. jno stsrructural changes, no chants to existing lighting & windowsDetails
change kitchen counter/ba vinets, bath lav/vanity work in unit #3. jno stsrructural changes, no chants to existing lighting & windows | $2,500 |
| Feb 9, 2007 | Never finaled issued Feb 2007, no final | 1522 07th Av | revision to pa# 2005/08/30/1598. rekicate washer-dryer. water heater. provide laundry sink. add bay window in kitchen. reconfigure 3rd floor bath. change family room to master bedroom for recording purposes only. final as built drawings.Details
revision to pa# 2005/08/30/1598. rekicate washer-dryer. water heater. provide laundry sink. add bay window in kitchen. reconfigure 3rd floor bath. change family room to master bedroom for recording purposes only. final as built drawings. | $2,000 |