Back to kitchen remodel contractors
Orchard Construction
- Based in
- Novato
- On San Francisco permits
- Jun 2018 to Nov 2025
- Last 24 months
- 9 permits filed
30 permits since 2000: 21 completed, 5 in progress, 3 never finaled, 1 expired or cancelled.
Of the 3 never-finaled permits, 3 are 5 to 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for kitchen remodel across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.
Kitchen remodel permits
5 kitchen remodel permits: 4 completed, 1 in progress. Typically 0 days from filing to permit and 330 days from permit to final inspection.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Mar 27, 2025 | In progress issued Mar 2025 | 100 Parker Av | replace in kind kitchen cabinets and kitchen floor tile. replace in kind bath, sink, tub and toilet. all fixtures being rpelaced in same locations.Details
replace in kind kitchen cabinets and kitchen floor tile. replace in kind bath, sink, tub and toilet. all fixtures being rpelaced in same locations. | $60,000 |
| Jan 21, 2025 | Completed final sign-off Dec 2025 | 10 Ina Ct | remodel to include (n) interior partitions, relocate (e) kitchen, relocate 2 (e) bathrooms and add 1 (n) bathroom at 2nd floor. convert (e) garage into conditioned space. adding 1 (n) skylight at rear roof and add 5 (n) windows throughout house not visible from street and replace (e) windows.Details
remodel to include (n) interior partitions, relocate (e) kitchen, relocate 2 (e) bathrooms and add 1 (n) bathroom at 2nd floor. convert (e) garage into conditioned space. adding 1 (n) skylight at rear roof and add 5 (n) windows throughout house not visible from street and replace (e) windows. | $100,000 |
| May 3, 2024 | Completed final sign-off Aug 2024 | 764 Clayton St | 2 bathroom + 1 kitchen remodel. replace in kind. all work on the 2nd floor. not moving walls. all fixtures in the same location. all work in kind. all work on 2nd fl. not moving walls. all fixtures in the same location/ place.Details
2 bathroom + 1 kitchen remodel. replace in kind. all work on the 2nd floor. not moving walls. all fixtures in the same location. all work in kind. all work on 2nd fl. not moving walls. all fixtures in the same location/ place. | $40,000 |
| Mar 3, 2022 | Completed final sign-off Mar 2023 | 259 Divisadero St | new interior wall opening between kitchen & living room and remove interior post on 2/f & 3/f.Details
new interior wall opening between kitchen & living room and remove interior post on 2/f & 3/f. | $15,000 |
| Nov 22, 2021 | Completed final sign-off Mar 2023 | 261 Divisadero St | units 261 and 263 divisadero st. doing 2 kitchen remodels and 2 bathroom remodels in both units. replace cabinets, replace plumbing fixtures. install new recessed cans and new floors. "remodel in kind"Details
units 261 and 263 divisadero st. doing 2 kitchen remodels and 2 bathroom remodels in both units. replace cabinets, replace plumbing fixtures. install new recessed cans and new floors. "remodel in kind" | $14,000 |