Northgate Development
- Based in
- Emeryville
- On San Francisco permits
- Aug 2007 to Mar 2025
- Last 24 months
- 1 permit filed
26 permits since 2000: 21 completed, 3 never finaled, 2 expired or cancelled.
Of the 3 never-finaled permits, 2 are 3 to 5 years old, 1 is 5 to 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Mar 31, 2025 | Completed final sign-off Apr 2025 | 1 Forest Knolls Dr | remove plywood siding from the front of the house 25 ft and west side of the house 12 ft from the 2nd fl. install 1/2 plywood nails 6-8 inches on the seams stucco per cbc requirements chapter 14 exterior wallsDetails
remove plywood siding from the front of the house 25 ft and west side of the house 12 ft from the 2nd fl. install 1/2 plywood nails 6-8 inches on the seams stucco per cbc requirements chapter 14 exterior walls | $10,000 |
| Nov 6, 2023 | Completed final sign-off Dec 2023 | 2229 15th St | a post is dry rotted (deck) 3 feet will be cut and will be replaced in kind the existing post is doubled in kind less than 50%Details
a post is dry rotted (deck) 3 feet will be cut and will be replaced in kind the existing post is doubled in kind less than 50% | $3,000 |
| Jul 3, 2023 | Completed final sign-off Aug 2023 | 57 Hillcrest Ct | repair (e) deck: installing (e) deck boards and railing with new. all work in-kind. 2 dft22 to post of railing. work less than 50%.Details
repair (e) deck: installing (e) deck boards and railing with new. all work in-kind. 2 dft22 to post of railing. work less than 50%. | $10,000 |
| Feb 27, 2023 | Completed final sign-off Apr 2023 | 148 Corwin St | complying with #9603216: replace guard rail installing dtt22 to the post wire railing.Details
complying with #9603216: replace guard rail installing dtt22 to the post wire railing. | $5,000 |
| Feb 27, 2023 | Completed final sign-off May 2023 | 150 Corwin St | complying with #202299822: less than 50% - in kind. adding joists to (e), repair and replace deck boards. installing guardrail dtt22 tention ties wire railings.Details
complying with #202299822: less than 50% - in kind. adding joists to (e), repair and replace deck boards. installing guardrail dtt22 tention ties wire railings. | $40,000 |
| Sep 19, 2022 | Completed final sign-off Oct 2022 | 57 Hillcrest Ct | rear deck - 50 percent (not to exceed) or less repair.Details
rear deck - 50 percent (not to exceed) or less repair. | $20,000 |
| Jul 25, 2022 | Completed final sign-off Sep 2022 | 1340 Utah St | front stairs installing new stringers, installing new threads, installing new 3/4 plywood on the landingDetails
front stairs installing new stringers, installing new threads, installing new 3/4 plywood on the landing | $10,000 |
| Jun 8, 2022 | Never finaled issued Jun 2022, no final | 1901 Franklin St | rebuilding porch floor. porch is inclused removing the non-bearing wall to original. install guardrail. removing and installing 2 patio doors.Details
rebuilding porch floor. porch is inclused removing the non-bearing wall to original. install guardrail. removing and installing 2 patio doors. | $20,000 |
| May 13, 2022 | Completed final sign-off Jun 2022 | 701 Moultrie St | repair deck under 50%. some deck boards 180 sqft. repair railing 30 lf redwood. install beam under deck, stairs, dtt22.Details
repair deck under 50%. some deck boards 180 sqft. repair railing 30 lf redwood. install beam under deck, stairs, dtt22. | $20,000 |
| May 13, 2022 | Never finaled issued Jun 2022, no final | 707 Grand View Av | removing 68 sqft deck boards. installing 68 sqft deck boards over existing waterproofed deck. no expansion of deck.Details
removing 68 sqft deck boards. installing 68 sqft deck boards over existing waterproofed deck. no expansion of deck. | $6,000 |
| Nov 24, 2021 | Completed final sign-off Jan 2022 | 148 Corwin St | deck adding joist to extg joist at 16 inches. o.c. replacing deck boards with ipe. repair extg joist to be remained under 50%.all existing joists to remain. no expansion.Details
deck adding joist to extg joist at 16 inches. o.c. replacing deck boards with ipe. repair extg joist to be remained under 50%.all existing joists to remain. no expansion. | $30,000 |
| Sep 27, 2021 | Completed final sign-off Apr 2022 | 551 Myra Wy | rebuilding front deck with pressure treated lumber composite deck boards and railing to comply with complaint 201843191.Details
rebuilding front deck with pressure treated lumber composite deck boards and railing to comply with complaint 201843191. | $10,000 |
| Sep 27, 2021 | Completed final sign-off Nov 2021 | 571 Douglass St | repair under 50% removing and replacing the deck boards. adding structural matel connectors closing the raisers.Details
repair under 50% removing and replacing the deck boards. adding structural matel connectors closing the raisers. | $5,000 |
| Aug 20, 2021 | Completed final sign-off Oct 2021 | 125 Mateo St | partial rebuilding of (e) rear deck: removing the deck boards and installing new deck boards & some of the joists. composite railing under 50%Details
partial rebuilding of (e) rear deck: removing the deck boards and installing new deck boards & some of the joists. composite railing under 50% | $10,000 |
| Jul 20, 2021 | Completed final sign-off Oct 2021 | 3731 16th St | rebuilding first floor deck in kind, new beam, new joist, stringer, stairs treads. comply with nov#202178681Details
rebuilding first floor deck in kind, new beam, new joist, stringer, stairs treads. comply with nov#202178681 | $10,000 |
| Apr 7, 2021 | Completed final sign-off Apr 2022 | 108 Burlwood Dr | building a deck for 1st and 2nd floor as well as changing 2 windows to sliding door and changing the tile siding to james haroy siding/the siding will be done to the east side of the house/composite and ipe wire deck railing.Details
building a deck for 1st and 2nd floor as well as changing 2 windows to sliding door and changing the tile siding to james haroy siding/the siding will be done to the east side of the house/composite and ipe wire deck railing. | $50,000 |
| Jan 26, 2021 | Completed final sign-off May 2021 | 341 Molimo Dr | removing existing deck & rebuilding deck same size.Details
removing existing deck & rebuilding deck same size. | $10,000 |
| Feb 19, 2020 | Completed final sign-off Jul 2020 | 60 Edgar Av | 1) replace ex railing to be built to third floor deck; 2) water proofing the (front) upper deck and installing 3/1 plywood. replace e plywood in kindDetails
1) replace ex railing to be built to third floor deck; 2) water proofing the (front) upper deck and installing 3/1 plywood. replace e plywood in kind | $10,000 |
| Jul 2, 2019 | Completed final sign-off Aug 2019 | 158 Langton St | installing simpson connectors dtt2, hangers, l 90, replacing 4x6 post with 6x6 post, removing 4x8 beam, installing new 4x8 beam p.t, new 2 piers 12"x48" dept, 2 cn66, piers 4-4 verticals, #3 rings at 6" o.c.Details
installing simpson connectors dtt2, hangers, l 90, replacing 4x6 post with 6x6 post, removing 4x8 beam, installing new 4x8 beam p.t, new 2 piers 12"x48" dept, 2 cn66, piers 4-4 verticals, #3 rings at 6" o.c. | $5,000 |
| Jun 17, 2019 | Completed final sign-off Jul 2019 | 456 Campbell Av | removing 2x4 redwood installing 2x6 redwood. installing rail 14' ft r5017.12 all work not visible from street in the rear of property.Details
removing 2x4 redwood installing 2x6 redwood. installing rail 14' ft r5017.12 all work not visible from street in the rear of property. | $3,000 |
| Aug 16, 2018 | Completed final sign-off Jan 2019 | 349 Mangels Av | bathroom remodel 5'x7' on the second floor.Details
bathroom remodel 5'x7' on the second floor. | $4,000 |
| Jun 15, 2018 | Completed final sign-off Aug 2018 | 349 Mangels Av | building patio, deck, redwood railing, planter 29 inches and fenceDetails
building patio, deck, redwood railing, planter 29 inches and fence | $8,000 |
| Apr 16, 2018 | Completed final sign-off Jun 2018 | 1590 Treat Av | to comply with 201709651 revision to 201712186728 removing non complying deck and building 9'x8' redwood deck and railing. (e) grade and no new retaining wall. no change to (e).Details
to comply with 201709651 revision to 201712186728 removing non complying deck and building 9'x8' redwood deck and railing. (e) grade and no new retaining wall. no change to (e). | |
| Jun 19, 2017 | Never finaled issued Jul 2017, no final | 175 Juanita Wy | demo a sunroom, building deck & stair, installing a patio door.Details
demo a sunroom, building deck & stair, installing a patio door. | $6,000 |
| Sep 7, 2007 | Expired or cancelled expired Aug 2010 | 454 Geary St | revised door for handycap access moved back into store as part of required work scope pa#2007/08/08/9202 for accessability compliance.Details
revised door for handycap access moved back into store as part of required work scope pa#2007/08/08/9202 for accessability compliance. | |
| Aug 8, 2007 | Expired or cancelled expired Aug 2010 | 454 Geary St | phase 1 remove wood store rack pannels, lino floor, install sheetrock walls, paint. install false ceiling + eletrical, install new cherry wood floor. mep. under seperate permit.Details
phase 1 remove wood store rack pannels, lino floor, install sheetrock walls, paint. install false ceiling + eletrical, install new cherry wood floor. mep. under seperate permit. | $75,000 |