Mc Guire And Hester
- Based in
- Alameda
- On San Francisco permits
- Aug 2003 to Jul 2026
- Last 24 months
- 5 permits filed
Also written on permits as: Mcguire And Hester.
22 permits since 2000: 14 completed, 8 in progress.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Jul 22, 2026 | Completed final sign-off Sep 2026 | 178 Brookdale Av | install about 2800 lineal feet of chain link fencing in preparation of future work in areas of vacant housing project. fence is 6ft tall with 12-foot wide vehicular access gates and 3-foot wide personnel access gates. (bldgs will be demoed in the future uder separate permit)Details
install about 2800 lineal feet of chain link fencing in preparation of future work in areas of vacant housing project. fence is 6ft tall with 12-foot wide vehicular access gates and 3-foot wide personnel access gates. (bldgs will be demoed in the future uder separate permit) | $170,000 |
| Jan 30, 2026 | In progress issued Apr 2026 | 1151 Buchanan St | documentation for deferred submital on (e) permit 2024-0129-4856 detailing the base plate and post-installed anchorage of the play equipment to the previously approved pier foundations.Details
documentation for deferred submital on (e) permit 2024-0129-4856 detailing the base plate and post-installed anchorage of the play equipment to the previously approved pier foundations. | $30,000 |
| Jan 30, 2026 | In progress issued Apr 2026 | 1225 Buchanan St | documentation for deferred submital on (e) permit 2024-0129-4855 detailing the base plate and post-installed anchorage of the play equipment to the previously permitted foundations.Details
documentation for deferred submital on (e) permit 2024-0129-4855 detailing the base plate and post-installed anchorage of the play equipment to the previously permitted foundations. | $30,000 |
| Feb 21, 2025 | Completed final sign-off May 2025 | 1652 Sunnydale Av | asbestos abatement for demo pa#202501218676.Details
asbestos abatement for demo pa#202501218676. | |
| Feb 7, 2025 | Completed final sign-off May 2025 | 1652 Sunnydale Av | mayor dir 17-02 priority project-demo a 2 story type 2 bldg.Details
mayor dir 17-02 priority project-demo a 2 story type 2 bldg. | $596,643 |
| Jan 29, 2024 | In progress issued Jun 2025 | 1225 Buchanan St | eddy to turk block contains: multi-sport half court, bbq & picnic area, young kids play area. complete renovation & addition of (n) program elements on all five blocks: a multi-sport half court,two childrens play areas,exercise area,full basketball court,stage,lawns, two picnic & bbq areas,...Details
eddy to turk block contains: multi-sport half court, bbq & picnic area, young kids play area. complete renovation & addition of (n) program elements on all five blocks: a multi-sport half court,two childrens play areas,exercise area,full basketball court,stage,lawns, two picnic & bbq areas,... | $850,000 |
| Jan 29, 2024 | In progress issued Jun 2025 | 871 Buchanan St | fulton to grove block contains: lawn, picnic area, community table, & communal gardens. complete renovation & addition of (n) program elements on all five blocks: a multi-sport half court,two childrens play areas,exercise area,full basketball court,stage,lawns, two picnic & bbq areas,...,Details
fulton to grove block contains: lawn, picnic area, community table, & communal gardens. complete renovation & addition of (n) program elements on all five blocks: a multi-sport half court,two childrens play areas,exercise area,full basketball court,stage,lawns, two picnic & bbq areas,..., | $650,000 |
| Jan 29, 2024 | In progress issued Jun 2025 | 951 Buchanan St | mcallister to fulton block contains: communal gardends, storage containers,stage,lawn, art plaza. complete renovation & addition of (n) program elements on all five blocks: a multi-sport half court,two childrens play areas,exercise area,full basketball court,stage,lawns, two picnic & bbq areas,...,Details
mcallister to fulton block contains: communal gardends, storage containers,stage,lawn, art plaza. complete renovation & addition of (n) program elements on all five blocks: a multi-sport half court,two childrens play areas,exercise area,full basketball court,stage,lawns, two picnic & bbq areas,..., | $1,750,000 |
| Jan 29, 2024 | In progress issued Jun 2025 | 1151 Buchanan St | turk to golden gate block contains: big kids play area, exercise area, plaza & communal gardens. complete renovation & addition of (n) program elements on all five blocks: a multi-sport half court,two childrens play areas,exercise area,full basketball court,stage,lawns, two picnic & bbq areas...,Details
turk to golden gate block contains: big kids play area, exercise area, plaza & communal gardens. complete renovation & addition of (n) program elements on all five blocks: a multi-sport half court,two childrens play areas,exercise area,full basketball court,stage,lawns, two picnic & bbq areas..., | $1,750,000 |
| Jan 10, 2024 | In progress issued Jun 2025 | 1051 Buchanan St | golden gate to mcallister block contains: full basketball court & picnic & bbq area. complete renovation & addition of (n) program elements on all five blocks: a multi-sport half court,two childrens play areas,exercise area,full basketball court,stage,lawns, two picnic & bbq areas,storage & park...,Details
golden gate to mcallister block contains: full basketball court & picnic & bbq area. complete renovation & addition of (n) program elements on all five blocks: a multi-sport half court,two childrens play areas,exercise area,full basketball court,stage,lawns, two picnic & bbq areas,storage & park..., | $1,000,000 |
| Sep 25, 2023 | In progress issued Sep 2024 | 1949 Sunnydale Av | mayor ed 17-02: construction of privately owned & maintained temporary access road (west access rd) as needed to maintain busing, vehicular, & pedestrian access through sunnydale hope sf site during construction of permanent city-dedicated streets under separate sip permitted through dpw.Details
mayor ed 17-02: construction of privately owned & maintained temporary access road (west access rd) as needed to maintain busing, vehicular, & pedestrian access through sunnydale hope sf site during construction of permanent city-dedicated streets under separate sip permitted through dpw. | $1,030,000 |
| Jul 12, 2021 | Completed final sign-off Oct 2024 | 1500 Sunnydale Av | priority processing. mayor's dir #17-02. erect a 2-story, type 3b,community center with childcare center. 1500 sunnydale aka 1550 sunnydaleDetails
priority processing. mayor's dir #17-02. erect a 2-story, type 3b,community center with childcare center. 1500 sunnydale aka 1550 sunnydale | $17,700,000 |
| Dec 12, 2012 | Completed final sign-off May 2015 | 2045 Evans Av | reroute ug fire lines for sprinkler addition to (e) bldg. installing new 6" ductile iron ug to (e) fdc's and system supply installing new 8" underground from evans stree to (e) fire pump. reference sprinkler system app.# 2012-1121-4716 ti pa# 2010-11-19-5309.Details
reroute ug fire lines for sprinkler addition to (e) bldg. installing new 6" ductile iron ug to (e) fdc's and system supply installing new 8" underground from evans stree to (e) fire pump. reference sprinkler system app.# 2012-1121-4716 ti pa# 2010-11-19-5309. | $25,000 |
| Nov 3, 2009 | Completed final sign-off Jun 2011 | 200 Folsom St | tjpa sign: greyhound. for location, see pa no. 200712211192s, sheet no. a-101.e key note (9).Details
tjpa sign: greyhound. for location, see pa no. 200712211192s, sheet no. a-101.e key note (9). | |
| Aug 4, 2009 | Completed final sign-off Jun 2011 | 200 Folsom St | tjpa sign: relocated l.e.d. display signs h-1 thru h-37. (see drawings attached to pa no. 200908044093)Details
tjpa sign: relocated l.e.d. display signs h-1 thru h-37. (see drawings attached to pa no. 200908044093) | |
| Aug 4, 2009 | Completed final sign-off Jan 2011 | 200 Folsom St | tjpa sign: transit information display signs i.1-5 thru i.1-9, i.2-1 thru i.2-37 and i.3-1. (see drawings attached to pa no. 200908044093)Details
tjpa sign: transit information display signs i.1-5 thru i.1-9, i.2-1 thru i.2-37 and i.3-1. (see drawings attached to pa no. 200908044093) | |
| Aug 4, 2009 | Completed final sign-off Jan 2011 | 200 Folsom St | tjpa sign: canopy bus stop id sign f1 thru f79. (see drawings attached to pa no. 200908044093)Details
tjpa sign: canopy bus stop id sign f1 thru f79. (see drawings attached to pa no. 200908044093) | |
| Aug 4, 2009 | Completed final sign-off Jun 2011 | 200 Folsom St | tjpa sign: street bus stop id signs g1 thru g11. (see drawings attached to pa no. 200908044093)Details
tjpa sign: street bus stop id signs g1 thru g11. (see drawings attached to pa no. 200908044093) | |
| Aug 4, 2009 | Completed final sign-off Jun 2011 | 200 Folsom St | tjpa sign: portal signs b1 thru b3. (see drawings attached to pa no. 200908044093)Details
tjpa sign: portal signs b1 thru b3. (see drawings attached to pa no. 200908044093) | |
| Aug 4, 2009 | Completed final sign-off Jun 2011 | 200 Folsom St | tjpa sign: primary site id sign a1 thru a3. (see attached drawings)Details
tjpa sign: primary site id sign a1 thru a3. (see attached drawings) | $297,500 |
| Aug 4, 2009 | Completed final sign-off Jan 2011 | 200 Folsom St | tjpa sign: primary directional/kiosk signs d-1 thru d-13. (see drawings attached to pa no. 200908044093)Details
tjpa sign: primary directional/kiosk signs d-1 thru d-13. (see drawings attached to pa no. 200908044093) | |
| Aug 15, 2003 | Completed final sign-off Oct 2005 | 1650 Owens St | all: storm drain service laterals to building from point of connectionat back of sidewalk. sanitaryDetails
all: storm drain service laterals to building from point of connectionat back of sidewalk. sanitary | $185,000 |