Jazz Builders Inc.
- Based in
- San Rafael
- On San Francisco permits
- May 2013 to May 2014
- Last 24 months
- 0 permits filed
3 permits since 2000: 1 completed, 2 never finaled.
Of the 2 never-finaled permits, 2 are over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for roof deck across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.
Roof deck permits
1 roof deck permit: 1 completed. Typically 273 days from filing to permit and 544 days from permit to final inspection.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| May 15, 2014 | Completed final sign-off Aug 2016 | 3211 Baker St | as per plans &spec rev dated 10/7/14: site permit-hori ext w/ roof deck & infill at 2/f--maher- compliance with ordinance no. 155-13 not required.Details
as per plans &spec rev dated 10/7/14: site permit-hori ext w/ roof deck & infill at 2/f--maher- compliance with ordinance no. 155-13 not required. | $250,000 |