Back to bathroom remodel contractors
Green City Construction Inc
- Based in
- Millbrae
- On San Francisco permits
- Dec 2010 to Jul 2026
- Last 24 months
- 12 permits filed
151 permits since 2000: 112 completed, 10 in progress, 22 never finaled, 7 expired or cancelled.
Of the 22 never-finaled permits, 1 is 3 to 5 years old, 16 are 5 to 10 years old, 5 are over 10 years old. 1 was filed but never issued.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for bathroom remodel across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Bathroom remodel permits
77 bathroom remodel permits: 61 completed, 6 in progress, 8 never finaled, 2 expired or cancelled. Typically 10 days from filing to permit and 281 days from permit to final inspection.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Jul 20, 2026 | In progress filed Jul 2026, not yet issued | 346 32nd Av | 2nd & 3rd floor interior remodel, open kitchen, dining & family room, relocate powder room, remodel stair at 2nd floor, remodel 3 bedrooms, add a new master bathroom, remodel existing roofdeck, replace all rear & side windows with aluminum & replace all doors, add a new deck at rear of the house forDetails
2nd & 3rd floor interior remodel, open kitchen, dining & family room, relocate powder room, remodel stair at 2nd floor, remodel 3 bedrooms, add a new master bathroom, remodel existing roofdeck, replace all rear & side windows with aluminum & replace all doors, add a new deck at rear of the house for | $120,000 |
| Jul 14, 2026 | In progress filed Jul 2026, not yet issued | 860 Moultrie St | to comply w/ nov# 20162001: 2nd floor remodel at kitchen, bathroom convert to master bath, new powder room, new window replacement at the back. attic floor lv remodel at bathroom, bedroom, convert new bedroom at front room space. new dormers at attic floor level.Details
to comply w/ nov# 20162001: 2nd floor remodel at kitchen, bathroom convert to master bath, new powder room, new window replacement at the back. attic floor lv remodel at bathroom, bedroom, convert new bedroom at front room space. new dormers at attic floor level. | $100,000 |
| Dec 26, 2025 | In progress issued Mar 2026 | 346 32nd Av | replace 10 front wood windows, door, garage door. 1st/f: rework entry/foyer, new interior hallway to habitable space bedroom, remodel e) stair to 2nd/f, relocate laundry area, remodel e) bedroom, new bathroom, remodel e) 1 car garage to 2 cars. basement/f: remodel e) exercise room w/ new bathroomDetails
replace 10 front wood windows, door, garage door. 1st/f: rework entry/foyer, new interior hallway to habitable space bedroom, remodel e) stair to 2nd/f, relocate laundry area, remodel e) bedroom, new bathroom, remodel e) 1 car garage to 2 cars. basement/f: remodel e) exercise room w/ new bathroom | $150,000 |
| Nov 13, 2025 | In progress issued Nov 2025 | 346 32nd Av | remodel kitchen & 2 bathrooms. tub to shower.Details
remodel kitchen & 2 bathrooms. tub to shower. | $35,000 |
| Nov 5, 2025 | In progress issued Nov 2025 | 860 Moultrie St | to comply with nov #20162001: remodel the (e) kitchen and two bathrooms. change tub to shower.Details
to comply with nov #20162001: remodel the (e) kitchen and two bathrooms. change tub to shower. | $35,000 |
| Jan 22, 2025 | Completed final sign-off Jul 2025 | 785 03rd Av | revision 202411014259- remodel family , addition of (n) bathroom and (n) laundry room located in basement and convert (e) laundry area into (n) office space and remodel garage area. to add (n) kitchenette on ground floorDetails
revision 202411014259- remodel family , addition of (n) bathroom and (n) laundry room located in basement and convert (e) laundry area into (n) office space and remodel garage area. to add (n) kitchenette on ground floor | $25,000 |
| Dec 12, 2024 | Completed final sign-off Apr 2025 | 88 Onondaga Av | unit #3: reinstall the tile for the bathroom. no moving walls/no layout change.Details
unit #3: reinstall the tile for the bathroom. no moving walls/no layout change. | $10,000 |
| Nov 1, 2024 | Completed final sign-off Jul 2025 | 785 03rd Av | 1 kitchen, 2 full bathrooms and 1 powder room remodel in kind. (everything the same)Details
1 kitchen, 2 full bathrooms and 1 powder room remodel in kind. (everything the same) | $35,000 |
| Sep 30, 2024 | Completed final sign-off Nov 2025 | 3300 Jackson St | ref 202405152223- ground floor (e) to remain except to provide a (n) elevator to 4 floors. 1st floor to redesign and remodel kitchen, bathroom, bedroom, powder room. 2nd floor to redesign and remodel bedrooms, bathrooms, laundry and (n) int. stair w/handrails to top floor. 3rd floor redesign (n) denDetails
ref 202405152223- ground floor (e) to remain except to provide a (n) elevator to 4 floors. 1st floor to redesign and remodel kitchen, bathroom, bedroom, powder room. 2nd floor to redesign and remodel bedrooms, bathrooms, laundry and (n) int. stair w/handrails to top floor. 3rd floor redesign (n) den | $250,000 |
| Aug 26, 2024 | In progress issued Aug 2024 | 88 Onondaga Av | unit 2 & 4: reinstall tile for bathroom, reinstall the (e) kitchen cabinet & counter top in kitchen. replace hard wood floor & repair drywall by water damaged for both units. all work is in-kind. no moving walls. no layout changes.Details
unit 2 & 4: reinstall tile for bathroom, reinstall the (e) kitchen cabinet & counter top in kitchen. replace hard wood floor & repair drywall by water damaged for both units. all work is in-kind. no moving walls. no layout changes. | $20,000 |
| May 15, 2024 | Completed final sign-off Nov 2025 | 3300 Jackson St | interior remodel basement improvement into habitable space for new bedroom w bath, family room with kitchenette, powder room and laundry area and wineroom, interior stairDetails
interior remodel basement improvement into habitable space for new bedroom w bath, family room with kitchenette, powder room and laundry area and wineroom, interior stair | $70,000 |
| Feb 6, 2024 | Completed final sign-off Nov 2025 | 3300 Jackson St | remodel the (e) kitchen, (e) 7 bathrooms rem., 1 bar and laundry room, replace 4 bedrooms & top floor family room, ceiling , and drywall repair. repair the roof less than 50 %. replace front facing garage door wood. replace family room sliding door wood and windows glazing with double-pane glass.Details
remodel the (e) kitchen, (e) 7 bathrooms rem., 1 bar and laundry room, replace 4 bedrooms & top floor family room, ceiling , and drywall repair. repair the roof less than 50 %. replace front facing garage door wood. replace family room sliding door wood and windows glazing with double-pane glass. | $65,000 |
| Jun 21, 2022 | Completed final sign-off Jul 2023 | 3150 Baker St | 1st/f: remodel bath, add family, office, 1 bedroom and 1 full bath. 2nd fl: remodel kitchen, bath, add 1 full bath. infill lightwell, repair deck.Details
1st/f: remodel bath, add family, office, 1 bedroom and 1 full bath. 2nd fl: remodel kitchen, bath, add 1 full bath. infill lightwell, repair deck. | $128,000 |
| Jun 17, 2022 | Completed final sign-off Jun 2024 | 1340 Dolores St | replace front windows + door with hung wood with og windows. remodel + add 1 bedroom, bathroom, family room, cooking counter with sink, at ground fl. remodel kitchen, bath & living room at 2nd fl. remodel 2 bathrooms + bedrooms at 3rd fl. repair (e) front + rear decks. repair front stair. 50% lessDetails
replace front windows + door with hung wood with og windows. remodel + add 1 bedroom, bathroom, family room, cooking counter with sink, at ground fl. remodel kitchen, bath & living room at 2nd fl. remodel 2 bathrooms + bedrooms at 3rd fl. repair (e) front + rear decks. repair front stair. 50% less | $200,000 |
| May 3, 2022 | Completed final sign-off Jul 2023 | 3150 Baker St | remodel three (e) bathrooms, one (e) kitchen, (e) laundry. replace six windows & 3 doors at rear & side of the house. not visible from street.Details
remodel three (e) bathrooms, one (e) kitchen, (e) laundry. replace six windows & 3 doors at rear & side of the house. not visible from street. | $55,000 |
| May 3, 2022 | Completed final sign-off Jun 2024 | 1340 Dolores St | to comply with nov# 202290102 & 202067043. repair guardrail. remodel existing 3 bathrooms, (1) kitchen, and laundry. replace 13 windows and 5 doors at rear & side of the house. no work visible from street.Details
to comply with nov# 202290102 & 202067043. repair guardrail. remodel existing 3 bathrooms, (1) kitchen, and laundry. replace 13 windows and 5 doors at rear & side of the house. no work visible from street. | $56,000 |
| Apr 27, 2022 | Completed final sign-off Jul 2023 | 1864 09th Av | remodel (e) kitchen, 3 bathrooms, & (e) luandry, replace the exterior 8 doors & 15 windows at rear and side of the house only.Details
remodel (e) kitchen, 3 bathrooms, & (e) luandry, replace the exterior 8 doors & 15 windows at rear and side of the house only. | $50,000 |
| Feb 28, 2022 | Completed final sign-off Jun 2023 | 1864 09th Av | replace extg windows and patio doors with aluminum clad wood window. 1st floor change to 2 car garage, add cooking & sink bar counter, remodel 2 bedrooms & bath. add family room & interior stair connecting to living room. add 3 dormer with windows; voluntariy strengthen each level by adding new plwDetails
replace extg windows and patio doors with aluminum clad wood window. 1st floor change to 2 car garage, add cooking & sink bar counter, remodel 2 bedrooms & bath. add family room & interior stair connecting to living room. add 3 dormer with windows; voluntariy strengthen each level by adding new plw | $80,000 |
| Aug 19, 2021 | Completed final sign-off Nov 2023 | 1296 Dolores St | g/f: new habitable space. interior remodel of (e) bathrooms, ktichen & add 2 new bathroom on 2/f & 3/f. replace (e) all (e) windows with alum clad wood. add a roof deck.Details
g/f: new habitable space. interior remodel of (e) bathrooms, ktichen & add 2 new bathroom on 2/f & 3/f. replace (e) all (e) windows with alum clad wood. add a roof deck. | $200,000 |
| May 21, 2021 | Completed final sign-off Nov 2022 | 149 03rd Av | improvement into habitable space on g/f per plans: interior remodel of kitchen, living room, 1/2bath,new laundry and new stair to g/f.remodeling (e) stair per plan 2/f.remodel bath,bedrooms; add (n) bath, new roof deck over (e) roof on 3/f.Details
improvement into habitable space on g/f per plans: interior remodel of kitchen, living room, 1/2bath,new laundry and new stair to g/f.remodeling (e) stair per plan 2/f.remodel bath,bedrooms; add (n) bath, new roof deck over (e) roof on 3/f. | $45,000 |
| Mar 11, 2021 | Completed final sign-off Aug 2021 | 307 Faxon Av | basement/1st floor improvement: convert storage area to office room. convert portion/utility area into exercise room. provide new half bathroom and laundry room.Details
basement/1st floor improvement: convert storage area to office room. convert portion/utility area into exercise room. provide new half bathroom and laundry room. | $15,000 |
| Feb 26, 2021 | Completed final sign-off Jan 2022 | 102 03rd Av | revision to pa# 202010196784: add 2nd level juliet balcony includes windows into french doors per plan at 2nd fl. change full bathroom to powder room split with wine room at 1st fl. 3rd fl roof convert to roof deck with 42" high solid railing. re-arrange master bathroom layout. add 2 skylights.Details
revision to pa# 202010196784: add 2nd level juliet balcony includes windows into french doors per plan at 2nd fl. change full bathroom to powder room split with wine room at 1st fl. 3rd fl roof convert to roof deck with 42" high solid railing. re-arrange master bathroom layout. add 2 skylights. | $5,000 |
| Dec 3, 2020 | Expired or cancelled withdrawn Jul 2023 | 1035 Natoma St | 1/f: remodel/improvement for habitable aera. add bedroom, family room, den, 2 bathrooms and laundry area per plan. 2/f remodel per plan and prev permit 202005267749.Details
1/f: remodel/improvement for habitable aera. add bedroom, family room, den, 2 bathrooms and laundry area per plan. 2/f remodel per plan and prev permit 202005267749. | $100,000 |
| Nov 25, 2020 | Expired or cancelled expired Sep 2024 | 1127 Burrows St | 1st fl: interior remodel/improvement space as per plan, provide new bedroom, family room, & full bathroom, replacement of window/door to the back and sheetrocking work.Details
1st fl: interior remodel/improvement space as per plan, provide new bedroom, family room, & full bathroom, replacement of window/door to the back and sheetrocking work. | $40,000 |
| Nov 24, 2020 | Completed final sign-off Mar 2023 | 536 40th Av | new staircase from 2nd to 1st floor. 2nd floor: move (e) kitchen from rear to front. remove (e) fireplace. convert (e) kitchen to study rm on 2nd flr. relocate (e) bathroom from 2nd floor to 1st. relocate (e) bedroom to 1st floor & incorporate open area.Details
new staircase from 2nd to 1st floor. 2nd floor: move (e) kitchen from rear to front. remove (e) fireplace. convert (e) kitchen to study rm on 2nd flr. relocate (e) bathroom from 2nd floor to 1st. relocate (e) bedroom to 1st floor & incorporate open area. | $72,000 |
| Oct 19, 2020 | Completed final sign-off Jan 2022 | 102 03rd Av | improvement into habitable space area as per plan: add 2 new bathrooms, 1 bedroom, family room at g/f. add a new 1/2 bath, connecting stair to basement to be reconfigured. new replacement plus french doors, windows at rear bedroom, remodel 2 (e) bathrooms on 3/f.Details
improvement into habitable space area as per plan: add 2 new bathrooms, 1 bedroom, family room at g/f. add a new 1/2 bath, connecting stair to basement to be reconfigured. new replacement plus french doors, windows at rear bedroom, remodel 2 (e) bathrooms on 3/f. | $70,000 |
| Oct 19, 2020 | Completed final sign-off Jul 2021 | 307 Faxon Av | revision to pa #202005277836 - add a new bathroom at 2/f & a new bathroom on 3/f. change the family room to officeDetails
revision to pa #202005277836 - add a new bathroom at 2/f & a new bathroom on 3/f. change the family room to office | $25,000 |
| Sep 3, 2020 | Completed final sign-off Jan 2022 | 102 03rd Av | remodeling (e) kitchen, two bathrooms, living room in kind, repair the front stair 50% or less. replace the existing windows with aluminum clad wood windows. replace the front with wood siding & replace the rear with stucco. hung windows no sliders - no changes to existing front windows with dividedDetails
remodeling (e) kitchen, two bathrooms, living room in kind, repair the front stair 50% or less. replace the existing windows with aluminum clad wood windows. replace the front with wood siding & replace the rear with stucco. hung windows no sliders - no changes to existing front windows with divided | $60,000 |
| Jun 1, 2020 | Completed final sign-off Jan 2022 | 1135 Pacific Av | remodel (e) kitchen. remove wall between living room and kitchen. relocate (e) bathroom & remodel (e) bedroom and relocate closet in bedroom. all interior work.Details
remodel (e) kitchen. remove wall between living room and kitchen. relocate (e) bathroom & remodel (e) bedroom and relocate closet in bedroom. all interior work. | $45,000 |
| May 27, 2020 | Completed final sign-off Jul 2021 | 307 Faxon Av | remodel the existing kitchen & bathroom in-kind.Details
remodel the existing kitchen & bathroom in-kind. | $20,000 |
| May 26, 2020 | Completed final sign-off Feb 2021 | 1035 Natoma St | to comply with nov# 202026344. remodeling the existing kitchen and 1 and 1/2 bathroom.Details
to comply with nov# 202026344. remodeling the existing kitchen and 1 and 1/2 bathroom. | $25,000 |
| Jan 29, 2020 | Never finaled issued Jul 2020, no final | 355 Byxbee St | remodel bathroom (e) bathroom @ 2/fDetails
remodel bathroom (e) bathroom @ 2/f | $6,000 |
| Dec 23, 2019 | Completed final sign-off Dec 2022 | 570 El Camino Del Mar | remodel (e) family room, add new bedroom, bath room and wine room at ground fl. remodel (e) bedrooms, bath room & kitchen, add new 1/2 bathroom at garage. replace s.o.g. at family rm area, adding plywood sheating (voluntary strenginening)Details
remodel (e) family room, add new bedroom, bath room and wine room at ground fl. remodel (e) bedrooms, bath room & kitchen, add new 1/2 bathroom at garage. replace s.o.g. at family rm area, adding plywood sheating (voluntary strenginening) | $35,000 |
| Mar 29, 2019 | Completed final sign-off Aug 2020 | 2746 Cabrillo St | interior remodel 1st flr and 2nd flr. with 3 full bathrooms one powder room, kitchen & 3 bedrooms. replace all windows (fiberglass wood)Details
interior remodel 1st flr and 2nd flr. with 3 full bathrooms one powder room, kitchen & 3 bedrooms. replace all windows (fiberglass wood) | $120,000 |
| Jan 29, 2019 | Completed final sign-off Jun 2019 | 671 15th Av | revision to pa 201812188643. add new bathroom at rear room at 3rd flrDetails
revision to pa 201812188643. add new bathroom at rear room at 3rd flr | $8,000 |
| Dec 18, 2018 | Completed final sign-off Jun 2019 | 671 15th Av | relocate (e) kitchen , convert (e) kitchen toom into new bedroom. remodel (e) bathroom w/washer/dryer stackable. ele,plm system updgrades. no exterior work.Details
relocate (e) kitchen , convert (e) kitchen toom into new bedroom. remodel (e) bathroom w/washer/dryer stackable. ele,plm system updgrades. no exterior work. | $20,000 |
| Jun 25, 2018 | Completed final sign-off Aug 2019 | 3945 23rd St | filled-in 1st floor below (e) deck. create a new master bedroom with new bath room. re-work (e) deck guardrailing to provide new glass railing & re-work waterproofing.Details
filled-in 1st floor below (e) deck. create a new master bedroom with new bath room. re-work (e) deck guardrailing to provide new glass railing & re-work waterproofing. | $58,000 |
| Jun 1, 2018 | Completed final sign-off Dec 2020 | 130 09th Av | 1st fl: add family rm, 1 bdrm, 1 full, one 1/2 bath. new elevator to all 3 floor. 2nd fl:remodel kitchen,bath,reconfigure space. new deck rear. 3rd fl rmdl kitchen bath, add 1 full bath, cantilever deck at rear. new roof deck and replace front windows in kind alum clad wood wndwsDetails
1st fl: add family rm, 1 bdrm, 1 full, one 1/2 bath. new elevator to all 3 floor. 2nd fl:remodel kitchen,bath,reconfigure space. new deck rear. 3rd fl rmdl kitchen bath, add 1 full bath, cantilever deck at rear. new roof deck and replace front windows in kind alum clad wood wndws | $100,000 |
| May 23, 2018 | Completed final sign-off Mar 2019 | 34 Walter St | rev #201710161350; interior remodel and adjustment layout add bath & bedroom at 4th floor. stucco the rear building 3-4 sprinkler under sep permit. seismic upgrade under pa #201710161350.Details
rev #201710161350; interior remodel and adjustment layout add bath & bedroom at 4th floor. stucco the rear building 3-4 sprinkler under sep permit. seismic upgrade under pa #201710161350. | $15,000 |
| Apr 24, 2018 | Completed final sign-off Aug 2019 | 3945 23rd St | remodel 2nd floor. add new bedrooms and bathroom, laundry at ground floor. replace windows. replace new rear deck, re-stucco rear house and replace the new roof. (tile to remain)Details
remodel 2nd floor. add new bedrooms and bathroom, laundry at ground floor. replace windows. replace new rear deck, re-stucco rear house and replace the new roof. (tile to remain) | $170,000 |
| Apr 17, 2018 | Never finaled issued May 2018, no final | 58 Lapidge St | remodel and move extg kitchen and powder room on 2nd floor. put in new slidiers in rear on 2nd floor. remodel 2 extg bathrooms on 3rd floor . put in spiral stairs to attic above. put in 3 dormers. dormer area is 17.36 y. of roof area & rear dormer is well within 457 setbackline.Details
remodel and move extg kitchen and powder room on 2nd floor. put in new slidiers in rear on 2nd floor. remodel 2 extg bathrooms on 3rd floor . put in spiral stairs to attic above. put in 3 dormers. dormer area is 17.36 y. of roof area & rear dormer is well within 457 setbackline. | $283,000 |
| Mar 2, 2018 | Completed final sign-off Mar 2018 | 575 35th Av | revision to opa 2017-0530-7931. add rear deck at 3rd fl. change location for bathroom, kitchen, doors and windows per plan. change the layout for bathroom for 2nd and 3rd floor.Details
revision to opa 2017-0530-7931. add rear deck at 3rd fl. change location for bathroom, kitchen, doors and windows per plan. change the layout for bathroom for 2nd and 3rd floor. | $2,000 |
| Jan 29, 2018 | Completed final sign-off Aug 2018 | 1556 Grove St | remodel existing kitchen and two bathrooms. in kindDetails
remodel existing kitchen and two bathrooms. in kind | $30,000 |
| Jan 16, 2018 | Never finaled issued Feb 2018, no final | 58 Lapidge St | create family room & bathroom on (e) 1st floor storage area. no exterior change. relocate (e) w&d & laundry sink to 1st flDetails
create family room & bathroom on (e) 1st floor storage area. no exterior change. relocate (e) w&d & laundry sink to 1st fl | $18,000 |
| Nov 16, 2017 | Completed final sign-off Mar 2022 | 138 Clinton Pk | add two adu units on ground floor per ordinance 162-16, (2) one-bedroom units; (1) kitchen & (1) bath for each unit.Details
add two adu units on ground floor per ordinance 162-16, (2) one-bedroom units; (1) kitchen & (1) bath for each unit. | $275,000 |
| Oct 19, 2017 | Completed final sign-off Aug 2018 | 844 Duncan St | modify approved permit 201510028711 with changes to a2.1. add wine cellar, widen entry door and sidelites. 1st fl- a2.2, move e fireplace, increase window size in bedrm 2 and 3, add 10" deep picture balcony, a2.3 relocate m bath, add new bath, take out e roof in front, extend deck to part ofDetails
modify approved permit 201510028711 with changes to a2.1. add wine cellar, widen entry door and sidelites. 1st fl- a2.2, move e fireplace, increase window size in bedrm 2 and 3, add 10" deep picture balcony, a2.3 relocate m bath, add new bath, take out e roof in front, extend deck to part of | $35,000 |
| Aug 16, 2017 | Completed final sign-off Aug 2018 | 306 Lawton St | residential renovation to duplex. primary work on 3rd fl unit : kitchen & bath renovations, add one (n) full bath. garage level (n) new partitions to create seperate garages. repair work on the 2nd fl unit. replace (e) 3rd flr windows(2) like for likeDetails
residential renovation to duplex. primary work on 3rd fl unit : kitchen & bath renovations, add one (n) full bath. garage level (n) new partitions to create seperate garages. repair work on the 2nd fl unit. replace (e) 3rd flr windows(2) like for like | $350,000 |
| Jun 5, 2017 | Completed final sign-off Jun 2018 | 762 31st Av | remodel kitchen, 2 1.2 bathrooms, 3 bedrooms, dining & living room at 2nd flr. add 2 bathrooms, 2 bedrooms and family room at graound floorDetails
remodel kitchen, 2 1.2 bathrooms, 3 bedrooms, dining & living room at 2nd flr. add 2 bathrooms, 2 bedrooms and family room at graound floor | $120,000 |
| May 30, 2017 | Completed final sign-off Feb 2018 | 575 35th Av | remodel & addition living. half bathroom, kitchen & dining & family room at ground floor. remodel 3 bedrooms, 2 bathrooms @ 2nd floor. remodel bedroom & add a bathroom & 3rd floor. replace front windows with aluminum clad wood window. no roof deckDetails
remodel & addition living. half bathroom, kitchen & dining & family room at ground floor. remodel 3 bedrooms, 2 bathrooms @ 2nd floor. remodel bedroom & add a bathroom & 3rd floor. replace front windows with aluminum clad wood window. no roof deck | $120,000 |
| Apr 27, 2017 | Completed final sign-off Aug 2017 | 90 Apollo St | remodel kitchen bathroom & add a new bath @ 2nd floor. replace the rear bedroom window & convert den to bedroomDetails
remodel kitchen bathroom & add a new bath @ 2nd floor. replace the rear bedroom window & convert den to bedroom | $35,000 |
| Mar 20, 2017 | Completed final sign-off Dec 2017 | 478 Anderson St | remodel kitchen, living room, dining room, bathroom, add a new bath @ 2nd floor. add 2 bathroom, 2 bedrooms, family room at ground floor. add a new roof deck. replace all windowsDetails
remodel kitchen, living room, dining room, bathroom, add a new bath @ 2nd floor. add 2 bathroom, 2 bedrooms, family room at ground floor. add a new roof deck. replace all windows | $120,000 |
| Feb 9, 2017 | Completed final sign-off Sep 2018 | 422 Jersey St | revision to 201612144924 general interio alterations to change home from (e) condition of 3 bedrooms, 2 baths to proposed condition of 4 bedrooms, 3 bathDetails
revision to 201612144924 general interio alterations to change home from (e) condition of 3 bedrooms, 2 baths to proposed condition of 4 bedrooms, 3 bath | $160,000 |
| Feb 3, 2017 | Completed final sign-off Mar 2021 | 1405 15th St | per unit legalization ordinance# 43-14. legalize (e) dwelling unit on the 1st floor to become 4 to 5 units building. legalize unit will be a (1) bedroom unit w/ kitchen & bath. soft story per 201701187351. maher n/a.Details
per unit legalization ordinance# 43-14. legalize (e) dwelling unit on the 1st floor to become 4 to 5 units building. legalize unit will be a (1) bedroom unit w/ kitchen & bath. soft story per 201701187351. maher n/a. | $150,000 |
| Dec 14, 2016 | Never finaled issued Dec 2016, no final | 422 Jersey St | remodel existing kitchen & 2 bathroom at 2nd floor and remodel existing bathroom at ground floor. replace doors & trims.Details
remodel existing kitchen & 2 bathroom at 2nd floor and remodel existing bathroom at ground floor. replace doors & trims. | $35,000 |
| Nov 14, 2016 | Completed final sign-off Sep 2019 | 3840 21st St | interior renovations: kitchen & bathrooms, add one half bath @ upper floor of unit.Details
interior renovations: kitchen & bathrooms, add one half bath @ upper floor of unit. | $55,000 |
| Oct 24, 2016 | Completed final sign-off Feb 2017 | 583 38th Av | remodeling kitchen, bedrooms, living room, dining room, bath room and add a new bath room laundry at 2nd floor. add new family room. 2 bedrooms and one bath at ground floor. replace all windows.Details
remodeling kitchen, bedrooms, living room, dining room, bath room and add a new bath room laundry at 2nd floor. add new family room. 2 bedrooms and one bath at ground floor. replace all windows. | $100,000 |
| Oct 19, 2016 | Never finaled issued Oct 2016, no final | 3840 21st St | remodeling the (e) kitchen & bathroom. no walls to be altered. no structural work.Details
remodeling the (e) kitchen & bathroom. no walls to be altered. no structural work. | $15,000 |
| Oct 2, 2015 | Never finaled issued Sep 2016, no final | 844 Duncan St | vertical addition to (e) bldg including bathroom. renovation & seismic retrofit to (e) structure & addition of 1-level with 1,000 sf of living space.Details
vertical addition to (e) bldg including bathroom. renovation & seismic retrofit to (e) structure & addition of 1-level with 1,000 sf of living space. | $575,000 |
| Sep 15, 2015 | Completed final sign-off Jul 2016 | 635 Dolores St | roof framing reconstruction for new skylights, localized interior altertations on second and gr fl. remodel e kitchen and bath on 2nd fl, new bathroom on gr fl, 6 new skylights, replace e windows. no exterior changesDetails
roof framing reconstruction for new skylights, localized interior altertations on second and gr fl. remodel e kitchen and bath on 2nd fl, new bathroom on gr fl, 6 new skylights, replace e windows. no exterior changes | $134,000 |
| Jul 14, 2015 | Completed final sign-off Nov 2016 | 11 Whitney St | renovate (e) kitchen & bath at 2nd floor. remodel (e) area to create (n) bedrooms, bath & laundry at 1st floor. infill below (e) building at rear. (n) interior stair from 1st to 2nd floor.Details
renovate (e) kitchen & bath at 2nd floor. remodel (e) area to create (n) bedrooms, bath & laundry at 1st floor. infill below (e) building at rear. (n) interior stair from 1st to 2nd floor. | $110,000 |
| Dec 31, 2014 | Completed final sign-off May 2018 | 366 Los Palmos Dr | create living space at garage level: add new bathroom and new bedroom. renovate kitchen, replace extg windows of west facade facing rear yard, new skylight. replace fixutres and tile at extg bath.front windows to be wood clad.Details
create living space at garage level: add new bathroom and new bedroom. renovate kitchen, replace extg windows of west facade facing rear yard, new skylight. replace fixutres and tile at extg bath.front windows to be wood clad. | $45,000 |
| Aug 1, 2014 | Completed final sign-off Aug 2018 | 287 14th Av | revision to app#201307232514. relocation of (3) skylights, new roof at rear deck 4th flr. add roof deck and a fire place. relocate bath @ 4th flr. enlarge window at study @ 2nd flr.removing staircase to yard not reqd. as an exit. revise patio door, add side lts. @ grnd floor- enlard bedroom due toDetails
revision to app#201307232514. relocation of (3) skylights, new roof at rear deck 4th flr. add roof deck and a fire place. relocate bath @ 4th flr. enlarge window at study @ 2nd flr.removing staircase to yard not reqd. as an exit. revise patio door, add side lts. @ grnd floor- enlard bedroom due to | $4,500 |
| Jun 30, 2014 | Never finaled issued Jul 2014, no final | 470 Alvarado St | horizontal addition to the side and rear deck on 3rd floor and roof deck per plan shown. remove bay windows on second floor and third floor at the rear per plan. raised the front door overhead opening per plan and elevation. remodel stairways, bathrooms, kitchen, add new skylight per plan.Details
horizontal addition to the side and rear deck on 3rd floor and roof deck per plan shown. remove bay windows on second floor and third floor at the rear per plan. raised the front door overhead opening per plan and elevation. remodel stairways, bathrooms, kitchen, add new skylight per plan. | $130,000 |
| Apr 9, 2014 | Completed final sign-off Feb 2015 | 631 15th Av | revision to 201312275157. new bath at gr floor, new 2x4 skylight at 3rd fl over master bath. revision to structural detailsDetails
revision to 201312275157. new bath at gr floor, new 2x4 skylight at 3rd fl over master bath. revision to structural details | $18,000 |
| Dec 27, 2013 | Completed final sign-off Feb 2015 | 631 15th Av | residential renovations to an extg 3 story duplex. work includes kitchen and bath renovations to both units and a recreation room in the extg garage, new interior stairs to connect 1st and 2nd flrs, removal of extg columns in garage and widening of extg garage doors.Details
residential renovations to an extg 3 story duplex. work includes kitchen and bath renovations to both units and a recreation room in the extg garage, new interior stairs to connect 1st and 2nd flrs, removal of extg columns in garage and widening of extg garage doors. | $115,000 |
| Dec 17, 2013 | Completed final sign-off Apr 2014 | 2937 Pine St | kitchen & bath interior remodel. add one (n) full bathroom per plan at 2nd floor. replace windows at rear & side of the house.Details
kitchen & bath interior remodel. add one (n) full bathroom per plan at 2nd floor. replace windows at rear & side of the house. | $40,000 |
| Nov 12, 2013 | Never finaled issued Nov 2013, no final | 1800 Pacific Av | unit 1003, remodel 2 existing bathrooms & kitchen - no structural work. no wall alteration or modificationDetails
unit 1003, remodel 2 existing bathrooms & kitchen - no structural work. no wall alteration or modification | $1,500 |
| May 31, 2013 | Completed final sign-off Aug 2013 | 2060 Union St | unit #5- remodel 1 nos of bathroom and laundryDetails
unit #5- remodel 1 nos of bathroom and laundry | $10,000 |
| Mar 22, 2013 | Completed final sign-off Aug 2013 | 143 Burnside Av | renovate existing kitchen and bath at 2nd level. replace windows at rear.Details
renovate existing kitchen and bath at 2nd level. replace windows at rear. | $40,000 |
| Feb 19, 2013 | Completed final sign-off May 2013 | 679 23rd Av | add a new bedroom, bath, laundry at ground fl. remodel kitchen, relocate half bath at 2nd fl. 2 new full baths and remodel (e) bath, add new laundry at 3rd fl. replace all new aluminum clad wood window, replace rear deck, new stucco at rear and side of houseDetails
add a new bedroom, bath, laundry at ground fl. remodel kitchen, relocate half bath at 2nd fl. 2 new full baths and remodel (e) bath, add new laundry at 3rd fl. replace all new aluminum clad wood window, replace rear deck, new stucco at rear and side of house | $72,000 |
| Jan 16, 2013 | Completed final sign-off Apr 2013 | 2232 15th St | remodeling the (e) 1/2 bathroom, full bathroom and ktichen in kind. same place.Details
remodeling the (e) 1/2 bathroom, full bathroom and ktichen in kind. same place. | $30,000 |
| Sep 19, 2012 | Completed final sign-off Nov 2012 | 835 41st Av | add new 1/2 bath & full bathroom, remodel the existing bedrooms at 2nd floor: add a new bedroom & remodel the (e) bedroom & family room at ground floor & add stucco at rear house. revision to pa# 201209058998.Details
add new 1/2 bath & full bathroom, remodel the existing bedrooms at 2nd floor: add a new bedroom & remodel the (e) bedroom & family room at ground floor & add stucco at rear house. revision to pa# 201209058998. | $25,000 |
| Sep 5, 2012 | Completed final sign-off Nov 2012 | 835 41st Av | remodel the 2nd floor kitchen, bathroom & remodel the ground floor bathroom. replace the 2nd floor bedroom & kitchen windows. replace the ground floor bedroom & family windows. repair the rear deckDetails
remodel the 2nd floor kitchen, bathroom & remodel the ground floor bathroom. replace the 2nd floor bedroom & kitchen windows. replace the ground floor bedroom & family windows. repair the rear deck | $25,780 |
| Apr 2, 2012 | Completed final sign-off Sep 2012 | 266 30th Av | remodel kitchen & bathroom. add new rear deck. replace 3rd floor ceiling sheetrock. replace the (e) side rear stair in kind. replace (e) french door in rear & replace 4 rear & side windows.Details
remodel kitchen & bathroom. add new rear deck. replace 3rd floor ceiling sheetrock. replace the (e) side rear stair in kind. replace (e) french door in rear & replace 4 rear & side windows. | $50,000 |
| Mar 6, 2012 | Completed final sign-off May 2012 | 315 De Long St | add one bedroom, one full bath, 1 family, & 1 storage, 1 laundry room at ground floor.Details
add one bedroom, one full bath, 1 family, & 1 storage, 1 laundry room at ground floor. | $32,000 |
| Jan 3, 2012 | Completed final sign-off Feb 2012 | 78 Kempton Av | remodel 1 kitchen and 1 bathroom at 2nd floor. lighting to comply with cec 150 kDetails
remodel 1 kitchen and 1 bathroom at 2nd floor. lighting to comply with cec 150 k | $18,300 |
| Dec 27, 2011 | Completed final sign-off Feb 2013 | 6276 03rd St | reove existing delapidated stoarge shed at front per nov 201166250 and app 201108152477. install new stucco at front side and rear of house. relocate kitchen and bath. replace rear/side wood stairsDetails
reove existing delapidated stoarge shed at front per nov 201166250 and app 201108152477. install new stucco at front side and rear of house. relocate kitchen and bath. replace rear/side wood stairs | $4,000 |