Permit GraphShortlistSan Francisco building permits since 2000

Frans Construction Inc.

Contractor license
597405
State license record
Based in
Eagle
On San Francisco permits
Oct 2012 to Jul 2026
Last 24 months
1 permit filed

18 permits since 2000: 16 completed, 2 never finaled.

Of the 2 never-finaled permits, 2 are 3 to 5 years old.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records

Permits filed each year

How long permits take

Median days to final inspection, citywideMedian days to permit issued, citywideThis contractor’s finished permits

Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.

Most recent permits

All
FiledOutcomeAddressWork described on the permitDeclared cost
Jul 31, 2026Completed
final sign-off Sep 2026
265 Winston Drconstruct 2 non load bearing walls with glass door and metal frame top portition, total approx. 22 ln ft. install 1 electrical switch to control 2 xsiting ceiling lights
Details
Permit
202607315920
Status
complete
Filed
Jul 31, 2026
Permit issued
Jul 31, 2026
Final sign-off
Sep 15, 2026
Declared cost
$10,000
Address
265 Winston Dr

construct 2 non load bearing walls with glass door and metal frame top portition, total approx. 22 ln ft. install 1 electrical switch to control 2 xsiting ceiling lights

Open the permit page

$10,000
Dec 22, 2022Completed
final sign-off Sep 2023
2500 Mission Stto comply with abe ordinance 51-16. reconstructing sloped sidewalk to correct cross slope issues, replacing door hardware and installing new door operator actuator bar. the entire slope of work is solely to remove barriers. ref abe 202207082138
Details
Permit
202212228985
Status
complete
Filed
Dec 22, 2022
Permit issued
Jul 17, 2023
Final sign-off
Sep 21, 2023
Declared cost
$40,000
Address
2500 Mission St

to comply with abe ordinance 51-16. reconstructing sloped sidewalk to correct cross slope issues, replacing door hardware and installing new door operator actuator bar. the entire slope of work is solely to remove barriers. ref abe 202207082138

Open the permit page

$40,000
Nov 21, 2022Completed
final sign-off Apr 2023
299 Valencia Stto comply with abe program. reconstruction of door landing and adjustment of door hardware. ref abe 202206151446
Details
Permit
202211216943
Status
complete
Filed
Nov 21, 2022
Permit issued
Mar 22, 2023
Final sign-off
Apr 17, 2023
Declared cost
$15,000
Address
299 Valencia St

to comply with abe program. reconstruction of door landing and adjustment of door hardware. ref abe 202206151446

Open the permit page

$15,000
Oct 25, 2022Completed
final sign-off Sep 2023
2323 Irving Stto comply with abe, abe 202206281817. replace storefront with new to accommodate ada compliant entrance door and installing new automatic power door operator buttons on bar.
Details
Permit
202210255079
Status
complete
Filed
Oct 25, 2022
Permit issued
Jul 13, 2023
Final sign-off
Sep 22, 2023
Declared cost
$35,000
Address
2323 Irving St

to comply with abe, abe 202206281817. replace storefront with new to accommodate ada compliant entrance door and installing new automatic power door operator buttons on bar.

Open the permit page

$35,000
Oct 24, 2022Completed
final sign-off Mar 2023
2166 Chestnut Stto comply with accessible business entrance program per ordinance 51-16 reconstruction of door hardware replacement for barrier removal abe# 202207071489
Details
Permit
202210244980
Status
complete
Filed
Oct 24, 2022
Permit issued
Mar 22, 2023
Final sign-off
Mar 30, 2023
Declared cost
$30,000
Address
2166 Chestnut St

to comply with accessible business entrance program per ordinance 51-16 reconstruction of door hardware replacement for barrier removal abe# 202207071489

Open the permit page

$30,000
Nov 4, 2021Completed
final sign-off Dec 2021
2500 Mission Strevision to pa 2021-1020-0840 change wall anchorage details
Details
Permit
202111041843
Status
complete
Filed
Nov 4, 2021
Permit issued
Nov 4, 2021
Final sign-off
Dec 17, 2021
Address
2500 Mission St

revision to pa 2021-1020-0840 change wall anchorage details

Open the permit page

Oct 20, 2021Never finaled
issued Oct 2021, no final
2500 Mission Stframe free standing wall move restroom toilet over 1/2 to meet ada
Details
Permit
202110200840
Status
issued
Filed
Oct 20, 2021
Permit issued
Oct 25, 2021
Declared cost
$6,500
Address
2500 Mission St

frame free standing wall move restroom toilet over 1/2 to meet ada

Open the permit page

$6,500
Oct 1, 2021Never finaled
issued Oct 2021, no final
1201 Market Stframe free standing wall to display. upgrade entry door opening force to 51lbs max.
Details
Permit
202110019627
Status
issued
Filed
Oct 1, 2021
Permit issued
Oct 21, 2021
Declared cost
$6,500
Address
1201 Market St

frame free standing wall to display. upgrade entry door opening force to 51lbs max.

Open the permit page

$6,500
Apr 29, 2021Completed
final sign-off Nov 2024
4669 Mission Stto comply w/abe202010022970 to provide an accessible entrance to the existing chase bank branch. work to include replacement of sidewalk and installation of automatic door openers.
Details
Permit
202104299556
Status
complete
Filed
Apr 29, 2021
Permit issued
May 20, 2024
Final sign-off
Nov 20, 2024
Declared cost
$75,000
Address
4669 Mission St

to comply w/abe202010022970 to provide an accessible entrance to the existing chase bank branch. work to include replacement of sidewalk and installation of automatic door openers.

Open the permit page

$75,000
Mar 1, 2019Completed
final sign-off May 2019
401 Divisadero St1st fl: interior remodel (ti) non-structural remove & replace furniture & cubical partitions, low voltage electrical (monitors).
Details
Permit
201903014138
Status
complete
Filed
Mar 1, 2019
Permit issued
Apr 10, 2019
Final sign-off
May 20, 2019
Declared cost
$91,000
Address
401 Divisadero St

1st fl: interior remodel (ti) non-structural remove & replace furniture & cubical partitions, low voltage electrical (monitors).

Open the permit page

$91,000
Mar 1, 2019Completed
final sign-off May 2019
1375 03rd St1st fl: non-structural remodel of bank including furniture & cubical wall, low voltage electricl (monitors).
Details
Permit
201903014136
Status
complete
Filed
Mar 1, 2019
Permit issued
Apr 10, 2019
Final sign-off
May 21, 2019
Declared cost
$60,000
Address
1375 03rd St

1st fl: non-structural remodel of bank including furniture & cubical wall, low voltage electricl (monitors).

Open the permit page

$60,000
Aug 30, 2018Completed
final sign-off Sep 2018
926 Taraval Strevision to app#201802080811. eliminating ada counter work from previously aproved permit
Details
Permit
201808308810
Status
complete
Filed
Aug 30, 2018
Permit issued
Aug 31, 2018
Final sign-off
Sep 4, 2018
Address
926 Taraval St

revision to app#201802080811. eliminating ada counter work from previously aproved permit

Open the permit page

Feb 8, 2018Completed
final sign-off Sep 2018
926 Taraval Stnew inclined walkway with handrails, new door closers, new isa sign new isa sign at accessible counter, relocating pass thru and new br glass at accessible counter
Details
Permit
201802080811
Status
complete
Filed
Feb 8, 2018
Permit issued
Aug 3, 2018
Final sign-off
Sep 4, 2018
Declared cost
$12,000
Address
926 Taraval St

new inclined walkway with handrails, new door closers, new isa sign new isa sign at accessible counter, relocating pass thru and new br glass at accessible counter

Open the permit page

$12,000
Jan 4, 2016Completed
final sign-off May 2016
2500 Mission Stinstall new furniture, finishes, & equipment, install 2 new e-atm's in lobby, providing structural fastening of e-atm's, ceiling work, removing 3 pendent lights, replacing accoustical tiles, relocating one wall washer, relocate power and data for new equipment, extg hvac to remain as is.
Details
Permit
201601046286
Status
complete
Filed
Jan 4, 2016
Permit issued
Mar 16, 2016
Final sign-off
May 5, 2016
Declared cost
$45,222
Address
2500 Mission St

install new furniture, finishes, & equipment, install 2 new e-atm's in lobby, providing structural fastening of e-atm's, ceiling work, removing 3 pendent lights, replacing accoustical tiles, relocating one wall washer, relocate power and data for new equipment, extg hvac to remain as is.

Open the permit page

$45,222
Sep 24, 2013Completed
final sign-off Oct 2013
1600 Van Ness Avrevise framing due to load bearing wall. original pa#201307121715-r1
Details
Permit
201309247647
Status
complete
Filed
Sep 24, 2013
Permit issued
Sep 24, 2013
Final sign-off
Oct 22, 2013
Declared cost
$1,500
Address
1600 Van Ness Av

revise framing due to load bearing wall. original pa#201307121715-r1

Open the permit page

$1,500
Jul 12, 2013Completed
final sign-off Oct 2013
1600 Van Ness Avceiling:replace tiles and patch repair paint grid for like new. apperance lighting:replace bulbs,ballast and lenses for consistant . appearance:hvac clean disfusers, replace as needed verify system is working. finishes. all nw finishes within tnt spce per finish plan toilet, full restroom upgrade.
Details
Permit
201307121715
Status
complete
Filed
Jul 12, 2013
Permit issued
Aug 7, 2013
Final sign-off
Oct 22, 2013
Declared cost
$152,000
Address
1600 Van Ness Av

ceiling:replace tiles and patch repair paint grid for like new. apperance lighting:replace bulbs,ballast and lenses for consistant . appearance:hvac clean disfusers, replace as needed verify system is working. finishes. all nw finishes within tnt spce per finish plan toilet, full restroom upgrade.

Open the permit page

$152,000
Nov 20, 2012Completed
final sign-off Mar 2013
1318 Stockton Stnew private office, patch & repair ceiling, new finishes & bank equipment.
Details
Permit
201211204565
Status
complete
Filed
Nov 20, 2012
Permit issued
Feb 25, 2013
Final sign-off
Mar 18, 2013
Declared cost
$64,513
Address
1318 Stockton St

new private office, patch & repair ceiling, new finishes & bank equipment.

Open the permit page

$64,513
Oct 10, 2012Completed
final sign-off Mar 2013
401 California Stminor interior remodel of existing chase bank, new offices, ceiling & finishes.
Details
Permit
201210101671
Status
complete
Filed
Oct 10, 2012
Permit issued
Jan 17, 2013
Final sign-off
Mar 8, 2013
Declared cost
$135,239
Address
401 California St

minor interior remodel of existing chase bank, new offices, ceiling & finishes.

Open the permit page

$135,239