Back to bathroom remodel contractors
D & H Construction
- Based in
- Berkeley
- On San Francisco permits
- May 2001 to Sep 2026
- Last 24 months
- 13 permits filed
86 permits since 2000: 47 completed, 16 in progress, 22 never finaled, 1 expired or cancelled.
Of the 22 never-finaled permits, 2 are 3 to 5 years old, 17 are 5 to 10 years old, 3 are over 10 years old. 11 were filed but never issued.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for bathroom remodel across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.
Bathroom remodel permits
5 bathroom remodel permits: 4 completed, 1 in progress. Typically 28 days from filing to permit and 365 days from permit to final inspection.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Sep 9, 2026 | In progress issued Sep 2026 | 1035 Van Ness Av | revision to bpa: 202510157392 - as requested by the project mechanical plan checker, this permit revsion documents the (e) ptac, or baseboard heater and bathroom exhaust fans that are remain in the project and removes the words ("design-build")Details
revision to bpa: 202510157392 - as requested by the project mechanical plan checker, this permit revsion documents the (e) ptac, or baseboard heater and bathroom exhaust fans that are remain in the project and removes the words ("design-build") | |
| Aug 19, 2022 | Completed final sign-off Dec 2022 | 216 Eddy St | minor revision to permit 202112084018 to reflect changes to bathrooms at mobility unit #205, smoke detectors, sidewalk.Details
minor revision to permit 202112084018 to reflect changes to bathrooms at mobility unit #205, smoke detectors, sidewalk. | $30,000 |
| Mar 9, 2022 | Completed final sign-off May 2023 | 422 Valencia St | exterior rehab, replace siding east elevation, (e) light wells. in kind window replacement, roof deck repair. dry rot &roof repair. interior rehab in-kind of all shared bath & toilet facilities, include accessibility upgrades & accessible restrooms. in kind rehab of all shared kitchens accessiblity.Details
exterior rehab, replace siding east elevation, (e) light wells. in kind window replacement, roof deck repair. dry rot &roof repair. interior rehab in-kind of all shared bath & toilet facilities, include accessibility upgrades & accessible restrooms. in kind rehab of all shared kitchens accessiblity. | $1,678,491 |
| Dec 27, 2019 | Completed final sign-off Jul 2024 | 1010 Market St | exterior: renovate entrance. repair windows. interior: upgrade entrance and common area. on residential floors remodel (e) units, bathrooms & replae entry doors; provide code required mobility & communication rooms. mep included. life-safety under a seperate permit.Details
exterior: renovate entrance. repair windows. interior: upgrade entrance and common area. on residential floors remodel (e) units, bathrooms & replae entry doors; provide code required mobility & communication rooms. mep included. life-safety under a seperate permit. | $10,700,000 |
| Aug 14, 2019 | Completed final sign-off Jul 2020 | 270 Turk St | install bathroom exhaust fans at all residential unitsDetails
install bathroom exhaust fans at all residential units | $240,000 |