- 6 permits filed
21 permits since 2000: 14 completed, 4 in progress, 2 never finaled, 1 expired or cancelled.
Of the 2 never-finaled permits, 2 are 3 to 5 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Jun 1, 2026 | In progress issued Jun 2026 | 2030 Golden Gate Av | recommencement and completion of work approved under pa# 2023-0720-2569 and # 2024-0415-9968Details
recommencement and completion of work approved under pa# 2023-0720-2569 and # 2024-0415-9968 | $17,000 |
| Aug 8, 2025 | In progress issued Sep 2025 | 3156 Clay St | revision to pa#201512306165,pa#202103126506,pa#202109208781,1)adding a rooftop curb for elevator & lifting unit access door 2) reconfigure the interior space of the unit #3156 in level 3, 3) reconfigure the space of unit 3760 on level 2. 4) reconfigure space unit 3758 on level 1, add elev. cntrl rm.Details
revision to pa#201512306165,pa#202103126506,pa#202109208781,1)adding a rooftop curb for elevator & lifting unit access door 2) reconfigure the interior space of the unit #3156 in level 3, 3) reconfigure the space of unit 3760 on level 2. 4) reconfigure space unit 3758 on level 1, add elev. cntrl rm. | |
| May 16, 2025 | In progress issued May 2025 | 3156 Clay St | recommencement and completion of work approved under bpa#: 201512306165, 202103126506 and 202109208781Details
recommencement and completion of work approved under bpa#: 201512306165, 202103126506 and 202109208781 | $162,000 |
| May 14, 2025 | Completed final sign-off Aug 2025 | 1396 Pacific Av | revision to permit 202501289196 to switch location of washer/dryer closet and water heater/furnance closet.Details
revision to permit 202501289196 to switch location of washer/dryer closet and water heater/furnance closet. | |
| May 9, 2025 | Completed final sign-off May 2025 | 55 Forest View Dr | second floor windows replaced in kind. to partially comply with code violation # 202536204Details
second floor windows replaced in kind. to partially comply with code violation # 202536204 | $5,000 |
| May 9, 2025 | Completed final sign-off May 2025 | 55 Forest View Dr | construction of a non load bearing wall with 20 min. door to create a hallway between garage and storage area. to partially comply with code violation # 202536204Details
construction of a non load bearing wall with 20 min. door to create a hallway between garage and storage area. to partially comply with code violation # 202536204 | $2,000 |
| Apr 15, 2024 | In progress issued May 2024 | 2030 Golden Gate Av | rebuild (e) front entry stairs and adjacent retaining walls. remove (e) interior spiral stairs and provide (n) interior elevator from 1st to 2nd flDetails
rebuild (e) front entry stairs and adjacent retaining walls. remove (e) interior spiral stairs and provide (n) interior elevator from 1st to 2nd fl | $20,000 |
| Jan 31, 2024 | Completed final sign-off Nov 2024 | 3367 Market St | replace 5 side windows in kind- not street visible. waterproof. trim and paint.Details
replace 5 side windows in kind- not street visible. waterproof. trim and paint. | $20,000 |
| Jul 20, 2023 | Never finaled issued Jul 2023, no final | 2030 Golden Gate Av | demo remodel 1/f & 3/f bathrooms, laypit of both to remai the same. new drains & fixtres to be installed in both showers waterproofing & tile in both bathrooms. new roliet in lower bthrm. replace cabinets in lwr ll wet bar. redirect (e) 30amp circuit for dryer outlet on top flr. no removal of wallDetails
demo remodel 1/f & 3/f bathrooms, laypit of both to remai the same. new drains & fixtres to be installed in both showers waterproofing & tile in both bathrooms. new roliet in lower bthrm. replace cabinets in lwr ll wet bar. redirect (e) 30amp circuit for dryer outlet on top flr. no removal of wall | $45,000 |
| Jun 21, 2023 | Never finaled issued Jun 2023, no final | 279 09th Av | to replace in kind less than 50% of an (e) deck due to dry rot (repair work)Details
to replace in kind less than 50% of an (e) deck due to dry rot (repair work) | $10,000 |
| Mar 21, 2022 | Completed final sign-off Jul 2022 | 215 Cherry St | replace in kind, tile, plumbing fixtures and electrical fixtures in existing ground floor bathroom. no walls to be removedDetails
replace in kind, tile, plumbing fixtures and electrical fixtures in existing ground floor bathroom. no walls to be removed | $10,000 |
| Aug 5, 2021 | Completed final sign-off Jul 2022 | 521 Euclid Av | repair dry rot on (e) deck at the rear of the property (less than 50%)Details
repair dry rot on (e) deck at the rear of the property (less than 50%) | $5,000 |
| Dec 24, 2019 | Completed final sign-off Aug 2020 | 1356 Dolores St | rev to pa201906113063: structural rev to roof framing. add lvl rafters to strengthen roof. add skylight 2'x4'. strengthen (e) footing t ground level. lighting changes.Details
rev to pa201906113063: structural rev to roof framing. add lvl rafters to strengthen roof. add skylight 2'x4'. strengthen (e) footing t ground level. lighting changes. | |
| Dec 24, 2019 | Expired or cancelled cancelled Jan 2026 | 1356 Dolores St | increase evaluation total to $200,000.00; additonal fees for $100k per bid c/n.Details
increase evaluation total to $200,000.00; additonal fees for $100k per bid c/n. | $100,000 |
| Sep 30, 2019 | Completed final sign-off May 2022 | 275 09th Av | revision to 201906133338. full exact replacement of rear 3 story addition with new construction due to poor condition of e structureDetails
revision to 201906133338. full exact replacement of rear 3 story addition with new construction due to poor condition of e structure | |
| Jun 13, 2019 | Completed final sign-off May 2022 | 275 09th Av | limited excavation at 1st floor to convert storage to living with 1 full bath & 1 bedroom. infill lightwell at 2nd & 3rd floors. renovate kitchen add 1/2 bath & rear deck at 2nd. add full bath & laundry at 3rd fl. reroof at rear, 3 new skylights. replace wndows and furnace wnd to match extg at frontDetails
limited excavation at 1st floor to convert storage to living with 1 full bath & 1 bedroom. infill lightwell at 2nd & 3rd floors. renovate kitchen add 1/2 bath & rear deck at 2nd. add full bath & laundry at 3rd fl. reroof at rear, 3 new skylights. replace wndows and furnace wnd to match extg at front | $250,000 |
| Jun 11, 2019 | Completed final sign-off Aug 2020 | 1356 Dolores St | dormer addition - replace existing front windows and door - new windows at rear. new skylight and interior remodeling.Details
dormer addition - replace existing front windows and door - new windows at rear. new skylight and interior remodeling. | $100,000 |
| Apr 1, 2019 | Completed final sign-off Nov 2020 | 1207 Thomas Av | install new piers and security fence.retaining wall. n/a for maher.Details
install new piers and security fence.retaining wall. n/a for maher. | $15,000 |
| Dec 27, 2018 | Completed final sign-off Oct 2019 | 450 Balboa St | add quarry tile flooring and cove base, frp pn walls, tile on walls plumbing (n) sinks, new equipment, new ada paddles hi/low, new countertops & cabinets, paintingDetails
add quarry tile flooring and cove base, frp pn walls, tile on walls plumbing (n) sinks, new equipment, new ada paddles hi/low, new countertops & cabinets, painting | $25,000 |
| Oct 23, 2018 | Completed final sign-off Feb 2019 | 2238 Polk St | 1) new exhaust fan. 2)new duct work.Details
1) new exhaust fan. 2)new duct work. | $10,000 |
| Mar 23, 2018 | Completed final sign-off Dec 2018 | 1401 Mission St | suite 1: 1st time t. i. of leased space on ground floor, recent construction mixed-use bldg, (n) interior metal frame partitions, finishes & lighting modification of (e) plumbingDetails
suite 1: 1st time t. i. of leased space on ground floor, recent construction mixed-use bldg, (n) interior metal frame partitions, finishes & lighting modification of (e) plumbing | $80,000 |