0 permits filed

19 permits since 2000: 11 completed, 3 never finaled, 5 expired or cancelled.

Of the 3 never-finaled permits, 2 are 3 to 5 years old, 1 is 5 to 10 years old.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records

Permits filed each year

How long permits take

Median days to final inspection, citywideMedian days to permit issued, citywideThis contractor’s finished permits

Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.

Where they worked

One dot per permit, coloured by the building type the city or the assessor gives it. A dark circle is several permits close together: click it to zoom in.

Most recent permits

AllDeck 1
FiledOutcomeAddressWork described on the permitDeclared cost
Dec 19, 2022Never finaled
issued Apr 2023, no final
410 China Basin Stadditional pv: 42 boviet 450w 18.9 kw. rooftop pv.
Details
Permit
202212198635
Permit issued
Apr 19, 2023

additional pv: 42 boviet 450w 18.9 kw. rooftop pv.

Open the permit page

$37,800
Aug 18, 2022Never finaled
issued Mar 2023, no final
2340 San Jose Avrevision to 201807033677 addendum# 8: 1) added solar stanchion structural design and layout to scope of work. 2)retated thermal tanks by 90 degree & relocated the expansion tanks and pump station. 3)added sheet structural drawings for level 9(sheets s2.09a, s2.09b & a2.09da) as reference.
Details
Permit
202208180854
Permit issued
Mar 16, 2023

revision to 201807033677 addendum# 8: 1) added solar stanchion structural design and layout to scope of work. 2)retated thermal tanks by 90 degree & relocated the expansion tanks and pump station. 3)added sheet structural drawings for level 9(sheets s2.09a, s2.09b & a2.09da) as reference.

Open the permit page

Jul 8, 2022Expired or cancelled
withdrawn Dec 2022
1204 Mason Stsolar thermal solar hot water system, 6 collectors, 1 140 gal tank
Details
Permit
202207088104

solar thermal solar hot water system, 6 collectors, 1 140 gal tank

Open the permit page

$14,742
Dec 13, 2021Completed
final sign-off Dec 2021
1615 Market Strev to pa 202012291878 single line eletrical drawing.
Details
Permit
202112134314
Permit issued
Dec 13, 2021
Final sign-off
Dec 15, 2021

rev to pa 202012291878 single line eletrical drawing.

Open the permit page

Jun 16, 2021Completed
final sign-off Jul 2023
99 Ocean Avrooftop solar 210 panels 82.67 kw. reference approved bpa#2019-1203-8490 9/29/21 this is a deffered submittal, revised cost to $1.00 permit fees paid on estimated cost $151.2k receipt #20210701-117ol dated 7/1/21 (aziz m.)
Details
Permit
202106162592
Permit issued
May 13, 2022
Final sign-off
Jul 17, 2023

rooftop solar 210 panels 82.67 kw. reference approved bpa#2019-1203-8490 9/29/21 this is a deffered submittal, revised cost to $1.00 permit fees paid on estimated cost $151.2k receipt #20210701-117ol dated 7/1/21 (aziz m.)

Open the permit page

$151,200
Mar 30, 2021Expired or cancelled
withdrawn May 2021
2340 San Jose Avinstallation of 39 solar thermal panels.
Details
Permit
202103307541

installation of 39 solar thermal panels.

Open the permit page

$95,823
Feb 23, 2021Completed
final sign-off May 2024
1629 Market Stinstallation of solar pv roof mounted system.
Details
Permit
202102235197
Permit issued
May 13, 2021
Final sign-off
May 16, 2024

installation of solar pv roof mounted system.

Open the permit page

$145,780
Dec 29, 2020Completed
final sign-off Dec 2021
1615 Market Stinstall 40 solar panels & 1 inverter. flat roof mounted with iron ridge ground mount racking. pv breaker provided on (e) electrical system.
Details
Permit
202012291878
Permit issued
Sep 1, 2021
Final sign-off
Dec 15, 2021

install 40 solar panels & 1 inverter. flat roof mounted with iron ridge ground mount racking. pv breaker provided on (e) electrical system.

Open the permit page

$173,000
Dec 29, 2020Never finaled
issued Jan 2021, no final
5880 03rd Strevised solar pv plans, page e202 construction change to pa# e202008209264
Details
Permit
202012291896
Permit issued
Jan 22, 2021

revised solar pv plans, page e202 construction change to pa# e202008209264

Open the permit page

$288,600
Dec 11, 2020Completed
final sign-off May 2024
1125 Stevenson Stinstallation of solar hot water system at roof. ref to pa #201811145895 (aka 1629 market st bldg #d)
Details
Permit
202012110860
Permit issued
May 27, 2021
Final sign-off
May 16, 2024

installation of solar hot water system at roof. ref to pa #201811145895 (aka 1629 market st bldg #d)

Open the permit page

$12,285
Dec 10, 2020Completed
final sign-off May 2024
1629 Market Stbldg #a: installation of solar hot water system.
Details
Permit
202012100766
Permit issued
May 7, 2021
Final sign-off
May 16, 2024

bldg #a: installation of solar hot water system.

Open the permit page

$29,484
Dec 10, 2020Completed
final sign-off May 2024
1629 Market Stbldg #b: installation of solar hot water system.
Details
Permit
202012100769
Permit issued
Mar 2, 2021
Final sign-off
May 16, 2024

bldg #b: installation of solar hot water system.

Open the permit page

$29,484
Nov 19, 2020Completed
final sign-off Mar 2022
975 Bryant Stanchorage of solar hot water collector racking system to underlying wood
Details
Permit
202011199303
Permit issued
Jan 4, 2021
Final sign-off
Mar 29, 2022

anchorage of solar hot water collector racking system to underlying wood

Open the permit page

$39,264
Feb 24, 2020Expired or cancelled
cancelled Jan 2026
979 Bryant Stinstallation of solar water heat system.
Details
Permit
202002245178

installation of solar water heat system.

Open the permit page

$39,264
Jan 22, 2020Expired or cancelled
cancelled Jan 2026
434 Minna Stanchorage of solar hot water colleciton racking system to under lying concrete deck. mechanical needed for interconnection of supplemental solar water heating system to existing domestic hot water system.
Details
Permit
202001222489

anchorage of solar hot water colleciton racking system to under lying concrete deck. mechanical needed for interconnection of supplemental solar water heating system to existing domestic hot water system.

Open the permit page

$66,339
Jan 17, 2020Expired or cancelled
cancelled Jan 2026
735 Davis Stinstallation of solar water heating system for new building currently in construction.
Details
Permit
202001172146

installation of solar water heating system for new building currently in construction.

Open the permit page

$44,172
Jun 25, 2019Completed
final sign-off Aug 2023
188 Octavia Stinstallation of solar hot heating system to supplement (e) hot water system in apartment building
Details
Permit
201906254301
Permit issued
Jan 29, 2020
Final sign-off
Aug 3, 2023

installation of solar hot heating system to supplement (e) hot water system in apartment building

Open the permit page

$38,855
Nov 29, 2018Completed
final sign-off Apr 2021
1178 Folsom Stinstallation of solar hot water heating system to supplement extg hot water system in apartment bldg.
Details
Permit
201811297031
Permit issued
Nov 29, 2018
Final sign-off
Apr 28, 2021

installation of solar hot water heating system to supplement extg hot water system in apartment bldg.

Open the permit page

$33,600
Jul 3, 2018Completed
final sign-off Jun 2024
2340 San Jose Avper ord# 17-02, parallel process, to erect 9 stories, no basement, type i-b, 131 units residential affordable housing project. ** maher: disturbance of at least 50 cu.yd. of soil, to dph **
Details
Permit
201807033677
Permit issued
Jan 31, 2019
Final sign-off
Jun 6, 2024

per ord# 17-02, parallel process, to erect 9 stories, no basement, type i-b, 131 units residential affordable housing project. ** maher: disturbance of at least 50 cu.yd. of soil, to dph **

Open the permit page

$55,000,000