Building California
- Based in
- Los Angeles
- On San Francisco permits
- Jan 2019 to Jun 2019
- Last 24 months
- 0 permits filed
4 permits since 2000: 4 completed.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for stairs across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.
Stairs permits
1 stairs permit: 1 completed. Typically 147 days from filing to permit and 17 days from permit to final inspection.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Jan 11, 2019 | Completed final sign-off Jun 2019 | 1555 05th Av | remove extg rotten non-functioning on grade stairway not serving any apartments.Details
remove extg rotten non-functioning on grade stairway not serving any apartments. | $2,000 |