- 9 permits filed
17 permits since 2000: 13 completed, 3 in progress, 1 never finaled.
Of the 1 never-finaled permit, 1 is 3 to 5 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Sep 1, 2026 | In progress issued Sep 2026 | 3300 Mission St | commencement or work not started under previously approved permit application number 202506118413.Details
commencement or work not started under previously approved permit application number 202506118413. | $10,000 |
| Jun 24, 2026 | Completed final sign-off Sep 2026 | 750 Golden Gate Av | to renew permit 202410022137.Details
to renew permit 202410022137. | |
| Apr 14, 2026 | Completed final sign-off Apr 2026 | 3433 03rd St | revision to permit # 202604018706 . add flextend location.Details
revision to permit # 202604018706 . add flextend location. | |
| Apr 1, 2026 | Completed final sign-off May 2026 | 3433 03rd St | revision to underground fire permit 202409110519: underground fire main for the new building.Details
revision to underground fire permit 202409110519: underground fire main for the new building. | |
| Jan 2, 2026 | Completed final sign-off May 2026 | 3433 03rd St | install a new sprinkler system in a new 2-story bldg, pa 202504144339 has already been issued for this scope but a sprinkler head needs to be removed from the elevator shaft so was directed by sffd to submit a new permitDetails
install a new sprinkler system in a new 2-story bldg, pa 202504144339 has already been issued for this scope but a sprinkler head needs to be removed from the elevator shaft so was directed by sffd to submit a new permit | |
| Oct 1, 2025 | Completed final sign-off Jul 2026 | 2401 Keith St | relocate 65 sprinklers in to new ceiling. ref# 202405021240Details
relocate 65 sprinklers in to new ceiling. ref# 202405021240 | $54,000 |
| Jun 11, 2025 | Completed final sign-off Sep 2026 | 3300 Mission St | install a new private fire line from the property line into the bldg. underground only ref pa # 2023-1025-9516Details
install a new private fire line from the property line into the bldg. underground only ref pa # 2023-1025-9516 | $10,000 |
| Jun 11, 2025 | In progress issued Jun 2025 | 967 Mission St | install a 6" dedicated ductile iron underground only. sprinkler under separate permit. ref pa # 2023-0922-7225Details
install a 6" dedicated ductile iron underground only. sprinkler under separate permit. ref pa # 2023-0922-7225 | $7,000 |
| May 14, 2025 | Completed final sign-off May 2026 | 3433 03rd St | installation of fire sprinkler system in new 2 story building. ref pa# 2024-0814-8660Details
installation of fire sprinkler system in new 2 story building. ref pa# 2024-0814-8660 | $150,000 |
| Oct 2, 2024 | In progress issued Oct 2024 | 750 Golden Gate Av | underground for fire service to feed a new bldg.Details
underground for fire service to feed a new bldg. | $10,000 |
| Sep 11, 2024 | Completed final sign-off May 2026 | 3433 03rd St | underground for private fire service to new building.Details
underground for private fire service to new building. | $10,000 |
| Jun 4, 2024 | Completed final sign-off Aug 2024 | 7070 California St | add 5 sprinklers under new floor in new office spaceDetails
add 5 sprinklers under new floor in new office space | $11,000 |
| May 22, 2024 | Completed final sign-off Jul 2024 | 240 Stockton St | ref pa# 202404260843 ti on 9th fl. relocate 8 sprinklers. remove 6 sprinklers & add 13 uprights in open office area.Details
ref pa# 202404260843 ti on 9th fl. relocate 8 sprinklers. remove 6 sprinklers & add 13 uprights in open office area. | $11,000 |
| Sep 11, 2023 | Completed final sign-off Sep 2023 | 278 Post St | 1/f and 2/f: demo of all existing pendent sprinklers and turning heads up for shell coverage.Details
1/f and 2/f: demo of all existing pendent sprinklers and turning heads up for shell coverage. | $20,000 |
| Dec 7, 2022 | Completed final sign-off Dec 2022 | 360 Post St | relocate 5 sprinkler heads and add 1 sprinkler per new floor planDetails
relocate 5 sprinkler heads and add 1 sprinkler per new floor plan | $6,000 |
| Nov 3, 2022 | Completed final sign-off Nov 2022 | 44 Tehama St | adding 2 heads in phone booths on level mezzanine adding 4 heads in phone booths on level 3Details
adding 2 heads in phone booths on level mezzanine adding 4 heads in phone booths on level 3 | $6,600 |
| Sep 27, 2022 | Never finaled issued Oct 2022, no final | 100 Montgomery St | 13/f: removing pendent sprinklers and installing uprights. 132 uprights and 11 pendents relocation. ref. permit 202208120417Details
13/f: removing pendent sprinklers and installing uprights. 132 uprights and 11 pendents relocation. ref. permit 202208120417 | $23,300 |