Am Construction Inc
- Based in
- Walnut Creek
- On San Francisco permits
- Apr 2010 to Jun 2025
- Last 24 months
- 4 permits filed
31 permits since 2000: 27 completed, 1 in progress, 2 never finaled, 1 expired or cancelled.
Of the 2 never-finaled permits, 1 is 3 to 5 years old, 1 is 5 to 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Jun 12, 2025 | Completed final sign-off Jun 2025 | 855 Rhode Island St | revise permit #202502251053 - removal of all kitchen cabinetry work from original scope.Details
revise permit #202502251053 - removal of all kitchen cabinetry work from original scope. | $20,000 |
| Feb 25, 2025 | Completed final sign-off Jun 2025 | 855 Rhode Island St | kitchen: r/r (e) cabinetry.demo pantry.bathroom: vanity,mirror.light fixtures and tilet to be replaced.laundry room relocation including ventless dryer.electrical instllation of gfci receptablce, switches, vacancy sensor and light fixtures.Details
kitchen: r/r (e) cabinetry.demo pantry.bathroom: vanity,mirror.light fixtures and tilet to be replaced.laundry room relocation including ventless dryer.electrical instllation of gfci receptablce, switches, vacancy sensor and light fixtures. | $36,500 |
| Feb 11, 2025 | Completed final sign-off Oct 2025 | 92 San Pablo Av | like for like bathroom remodel including: new shower pan, toilet installation, pedestal sink and new flooring. outlets to be updated to gfci and sensor switch to be included, no wall demolition or construction, no change in plumbing fixture count.Details
like for like bathroom remodel including: new shower pan, toilet installation, pedestal sink and new flooring. outlets to be updated to gfci and sensor switch to be included, no wall demolition or construction, no change in plumbing fixture count. | $12,500 |
| Jan 21, 2025 | Completed final sign-off Apr 2025 | 121 Seal Rock Dr | kitchen upgrade, like for like: new tile, appliances, can light installation and shelving removal.Details
kitchen upgrade, like for like: new tile, appliances, can light installation and shelving removal. | $32,000 |
| Apr 7, 2024 | In progress issued Oct 2024 | 1466 15th Av | partial conversion of(e)unconditioned 1st fl to(n)conditioned area.(n)conditioned areas include 1b,1ba,a music & family room and wetbar.103 sf addition to (e)garage & 106 sf rear addition to conditioned space.demolition of(e) stairs in the lgihtway.interior remodel of upper level.Details
partial conversion of(e)unconditioned 1st fl to(n)conditioned area.(n)conditioned areas include 1b,1ba,a music & family room and wetbar.103 sf addition to (e)garage & 106 sf rear addition to conditioned space.demolition of(e) stairs in the lgihtway.interior remodel of upper level. | $200,000 |
| Apr 2, 2024 | Completed final sign-off Jun 2024 | 601 Van Ness Av | like for like kitchen and bathroom. bathroom includes: (1) bathtub, (1) vanity, and (1) toilet. kitchen includes: sink, (4) new lights. outlets upgraded throughout. no moving wallsDetails
like for like kitchen and bathroom. bathroom includes: (1) bathtub, (1) vanity, and (1) toilet. kitchen includes: sink, (4) new lights. outlets upgraded throughout. no moving walls | $40,000 |
| Feb 21, 2024 | Completed final sign-off Aug 2025 | 440 Missouri St | exisiting bathroom demolished, new bathroom fabricatedd to be replace it. kitchen remodel, including supply relocation. new appliance installation.Details
exisiting bathroom demolished, new bathroom fabricatedd to be replace it. kitchen remodel, including supply relocation. new appliance installation. | $85,000 |
| Oct 27, 2023 | Completed final sign-off Dec 2024 | 2052 Greenwich St | revision to 202308094078. replace (e) door with window. (n) sliding door at exterior. (n) glass door replaces (e) wood door. revised lighting plan.Details
revision to 202308094078. replace (e) door with window. (n) sliding door at exterior. (n) glass door replaces (e) wood door. revised lighting plan. | |
| Aug 9, 2023 | Completed final sign-off Jan 2025 | 2052 Greenwich St | creating new work room at level 1, door and window at rear facade, new lighting and power at work room. voluntary seismic retrofit. new bathroom at level 1, replace garage door. replace gas furnaces for both units.Details
creating new work room at level 1, door and window at rear facade, new lighting and power at work room. voluntary seismic retrofit. new bathroom at level 1, replace garage door. replace gas furnaces for both units. | $58,000 |
| Jun 7, 2023 | Completed final sign-off Jul 2024 | 849 Dolores St | conversion of addition to existing 527 sf family room & bath to become a 550 sf adu unit per oridinance 95-17.Details
conversion of addition to existing 527 sf family room & bath to become a 550 sf adu unit per oridinance 95-17. | $70,000 |
| Feb 28, 2023 | Never finaled issued Jul 2023, no final | 415 Tehama St | all 6 units: interior alterations, demo existing lath and plaster. replace with drywall sheetboard, partial demolition of interior partitions, new interior partitions. bathroom and kitchen renovations, window replacement in-kind. front windows facing street to be wood w/integrated ogee lugsDetails
all 6 units: interior alterations, demo existing lath and plaster. replace with drywall sheetboard, partial demolition of interior partitions, new interior partitions. bathroom and kitchen renovations, window replacement in-kind. front windows facing street to be wood w/integrated ogee lugs | $203,000 |
| Dec 22, 2022 | Completed final sign-off Jan 2023 | 51 Seward St | 15 windows to be replaced like for like . no location or size adjustments. u-factor 0.30 max. not visible from the street.Details
15 windows to be replaced like for like . no location or size adjustments. u-factor 0.30 max. not visible from the street. | $5,200 |
| Jun 21, 2022 | Completed final sign-off Mar 2025 | 4945 Anza St | to comply with nov# 2020058331. legalization of 2nd per density unit at 1st level. legalize rear stairs. new read door an balcony @ 2nd level.Details
to comply with nov# 2020058331. legalization of 2nd per density unit at 1st level. legalize rear stairs. new read door an balcony @ 2nd level. | $65,000 |
| Jun 30, 2021 | Completed final sign-off Dec 2021 | 270 San Leandro Wy | four bathrooms, in kind remodel. all cabinerty hardware flooring anad fixtures to be replaced with new. all electrical and plumbing locations to remain as is.Details
four bathrooms, in kind remodel. all cabinerty hardware flooring anad fixtures to be replaced with new. all electrical and plumbing locations to remain as is. | $6,000 |
| Jun 4, 2021 | Completed final sign-off Aug 2021 | 51 Seward St | reface existing wooden planks on the deck, replace if too damaged. fabricate redwood walkwayDetails
reface existing wooden planks on the deck, replace if too damaged. fabricate redwood walkway | $45,000 |
| Aug 19, 2019 | Completed final sign-off Jul 2020 | 173 Lexington St | to comply with physical inspection report cc-8359.Details
to comply with physical inspection report cc-8359. | $18,000 |
| Aug 19, 2019 | Completed final sign-off Jul 2020 | 171 Lexington St | to comply with physical inspection report cc-8358.Details
to comply with physical inspection report cc-8358. | $12,000 |
| Apr 17, 2019 | Never finaled issued Apr 2019, no final | 418 Corbett Av | demo all tile in bathroom/replace all areas affected by repair leak from roof. replace window frame- from dry rot. all work in-kind.Details
demo all tile in bathroom/replace all areas affected by repair leak from roof. replace window frame- from dry rot. all work in-kind. | $4,000 |
| Mar 26, 2019 | Completed final sign-off Aug 2020 | 51 Seward St | interior remodel - reconfigure bathrooms, relocate laundry, remodel kitchen, provide new rear facing windows, skylight, raised deck 3 feet above grade, new fenceDetails
interior remodel - reconfigure bathrooms, relocate laundry, remodel kitchen, provide new rear facing windows, skylight, raised deck 3 feet above grade, new fence | $60,000 |
| Jul 20, 2018 | Completed final sign-off Oct 2018 | 1821 15th St | #16 -interior remodel to upper floor 4th floor master bathroom.Details
#16 -interior remodel to upper floor 4th floor master bathroom. | $10,000 |
| Aug 22, 2017 | Completed final sign-off Jan 2018 | 1000 Steiner St | interior renovation 2nd fl unit 202. no struc, kitchen remodel new cab,cntr top, shift wall btwn mstr bath,guest bath, remodel baths. install hardwood flr, replace tiles at (e) fire place, install hearth, relocate door at guest rm hallway closetDetails
interior renovation 2nd fl unit 202. no struc, kitchen remodel new cab,cntr top, shift wall btwn mstr bath,guest bath, remodel baths. install hardwood flr, replace tiles at (e) fire place, install hearth, relocate door at guest rm hallway closet | $20,000 |
| Feb 8, 2017 | Expired or cancelled expired Mar 2023 | 30 Randolph St | comply w/nov #201495481 - new in-law unit conversion of 437 sq ft on ground floor/basement including 1 bedroom, 1 bathroom, 1 kitchen. removal & demolition of existing walls. new walls as per plans. sprinkler on deferred submittal.Details
comply w/nov #201495481 - new in-law unit conversion of 437 sq ft on ground floor/basement including 1 bedroom, 1 bathroom, 1 kitchen. removal & demolition of existing walls. new walls as per plans. sprinkler on deferred submittal. | $54,500 |
| Nov 16, 2016 | Completed final sign-off Oct 2017 | 180 Mangels Av | reroofingDetails
reroofing | $2,500 |
| Dec 17, 2015 | Completed final sign-off May 2016 | 605 Fell St | building: (n) sheetrock and insulation on 3 walls of rm and ceiling (80 sq.ft). replace (2) windows in kind. windows to comply with section 1013.8. plumbing: add (10 spigot at garage outside (for garden hose). electrical: replace knor + tube in one room. add hardwired smoke alarm.Details
building: (n) sheetrock and insulation on 3 walls of rm and ceiling (80 sq.ft). replace (2) windows in kind. windows to comply with section 1013.8. plumbing: add (10 spigot at garage outside (for garden hose). electrical: replace knor + tube in one room. add hardwired smoke alarm. | $7,000 |
| Dec 7, 2015 | Completed final sign-off Dec 2016 | 163 Mangels Av | replace in kind (e) wood decks & connecting metal spiral stair. replace siding, dryrot on south facing kitchen walls. no new fire walls.Details
replace in kind (e) wood decks & connecting metal spiral stair. replace siding, dryrot on south facing kitchen walls. no new fire walls. | $8,500 |
| Nov 24, 2015 | Completed final sign-off May 2016 | 1742 La Salle Av | change 4 windows - (2 in bedroom, 2 in den) in-kind, not visible from street. u-factor 0.32 max.Details
change 4 windows - (2 in bedroom, 2 in den) in-kind, not visible from street. u-factor 0.32 max. | $750 |
| Aug 26, 2015 | Completed final sign-off Jun 2016 | 1742 La Salle Av | unit 1742: revision to 2009 0721 3063 & 201508214961: relocate kitchen & bathroom, create laundry closet, replace damaged shet rock. remove vanity.Details
unit 1742: revision to 2009 0721 3063 & 201508214961: relocate kitchen & bathroom, create laundry closet, replace damaged shet rock. remove vanity. | $32,000 |
| Jun 4, 2015 | Completed final sign-off Jan 2016 | 605 Fell St | structural strengthening at rear of building. repair portion of e non conforming stairs at rear in kindDetails
structural strengthening at rear of building. repair portion of e non conforming stairs at rear in kind | $30,000 |
| Dec 24, 2013 | Completed final sign-off Oct 2017 | 180 Mangels Av | vertical addition and interior remodel. replace (e) pitched roof / attic with full height story w/flat roof.Details
vertical addition and interior remodel. replace (e) pitched roof / attic with full height story w/flat roof. | $150,000 |
| Sep 23, 2013 | Completed final sign-off Jan 2014 | 180 Mangels Av | foundation retrofitDetails
foundation retrofit | $28,500 |
| Apr 6, 2010 | Completed final sign-off Jun 2018 | 175 Mangels Av | alteration to existing single family dwelling, including replace interior stair, remodel kitchen & addition to rear including new bedroom and bathroom and associated title 24. add dormer above stair.Details
alteration to existing single family dwelling, including replace interior stair, remodel kitchen & addition to rear including new bedroom and bathroom and associated title 24. add dormer above stair. | $76,500 |