Back to kitchen remodel contractors
Advanced Restoration Inc
- Based in
- San Jose
- On San Francisco permits
- Jun 2012 to Sep 2026
- Last 24 months
- 7 permits filed
31 permits since 2000: 24 completed, 2 in progress, 3 never finaled, 2 expired or cancelled.
Of the 3 never-finaled permits, 2 are 5 to 10 years old, 1 is over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for kitchen remodel across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.
Kitchen remodel permits
5 kitchen remodel permits: 4 completed, 1 never finaled. Typically 0 days from filing to permit and 66 days from permit to final inspection.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Sep 26, 2025 | Completed final sign-off Dec 2025 | 2121 03rd St | unit 319- drywall repair replace electrical outlets, kitchen cabinets, and countertops replace flooring, water damage, paint entire unit to abate nov 202534474. replace in-kind.Details
unit 319- drywall repair replace electrical outlets, kitchen cabinets, and countertops replace flooring, water damage, paint entire unit to abate nov 202534474. replace in-kind. | $50,572 |
| Nov 17, 2016 | Never finaled issued Nov 2016, no final | 1494 Revere Av | fire damage repairs: some framing, electrical-all led lights, plumbing, mechanical, drywall and replace insulation. kitchen and bath remodel & drywall in living & two other rooms.Details
fire damage repairs: some framing, electrical-all led lights, plumbing, mechanical, drywall and replace insulation. kitchen and bath remodel & drywall in living & two other rooms. | $45,000 |
| Aug 10, 2015 | Completed final sign-off Nov 2015 | 1739 40th Av | reinstall lower kitchen cabinets. drywall repair, insulation, reset kitchen sink, rewier and new panelDetails
reinstall lower kitchen cabinets. drywall repair, insulation, reset kitchen sink, rewier and new panel | $40,000 |
| May 16, 2013 | Completed final sign-off Apr 2014 | 554 Commercial St | for fire damage repair - dry wall, plumbing (replacing kitchen sink and drain) rewire - electrical, replacing ducting and servicing unit.Details
for fire damage repair - dry wall, plumbing (replacing kitchen sink and drain) rewire - electrical, replacing ducting and servicing unit. | $100,000 |
| Dec 17, 2012 | Completed final sign-off Jan 2013 | 210 Lobos St | replaced insulation & sheetrock in bathroom walls & partial kitchen wall & partial kitchen wall. at east side exterior wall i 100 sq ft due to fire damage. repair & replace only. siding replace in kind.Details
replaced insulation & sheetrock in bathroom walls & partial kitchen wall & partial kitchen wall. at east side exterior wall i 100 sq ft due to fire damage. repair & replace only. siding replace in kind. | $20,000 |