Block 8709, lot 019
1470 Owens St
28 permits filed for this property since 2000.
CompletedIn progressNever finaledExpired or cancelled
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| May 2, 2022 | Completed final sign-off Aug 2022 | 1470 Owens St | Truebeck Construction | temporary(2) construction of trailers on the roof of adjacement parking garage at 1470 owens st. | $52,000 |
| Feb 21, 2020 | Completed final sign-off Jun 2020 | 1470 Owens St | Truebeck Construction | revision to app#201806010826. s1 and s2, addebd #1 and #2. an ejector pump added to help with movement of waste water out to the manhole. | $20,000 |
| Jan 23, 2020 | Completed final sign-off Mar 2020 | 1470 Owens St | Truebeck Construction | revision to pa 2018-0601-0826 to add wind screens at 4th fl elevators | $1,500 |
| Dec 26, 2019 | Completed final sign-off Jun 2020 | 1470 Owens St | Truebeck Construction | administrative permit to demonstrate passing test coverage and that no errcs for the parking structural is required. related to site permit app#201806010826 | |
| Oct 31, 2019 | Completed final sign-off Jun 2020 | 1470 Owens St | Truebeck Construction | rev to pa# 201806010826 add #2, misc rev have been made to the archtictural and security drawings, changes include: security cameras, emergency blue phones added to levels 2-4, adjacaent to elevators, card readers were added to a number at doors, smoke detectors, access door | |
| Oct 8, 2019 | Completed final sign-off Jun 2020 | 1470 Owens St | Truebeck Construction | evacuation signage on plan ref pa 2018-0601-0826 | $2,500 |
| Sep 25, 2019 | Completed final sign-off Aug 2020 | 1470 Owens St | Truebeck Construction | deferred submittal to pa 2018-0601-0826 green screen item #12 | $5,000 |
| Sep 18, 2019 | Completed final sign-off Jan 2020 | 1470 Owens St | Ad Art Inc. | install ground non electric double faced sign | $5,000 |
| Aug 21, 2019 | Completed final sign-off Feb 2020 | 1470 Owens St | Truebeck Construction | install non electric sign(s) for "1470" | $1,000 |
| Aug 21, 2019 | Completed final sign-off Feb 2020 | 1470 Owens St | Truebeck Construction | parking signage permit for 201806010826 | $2,000 |
| Aug 21, 2019 | Completed final sign-off Feb 2020 | 1470 Owens St | Truebeck Construction | install non electric sign(s) for parking | $1,000 |
| Aug 7, 2019 | Completed final sign-off Feb 2020 | 1470 Owens St | Truebeck Construction | deferred submittal to pa 2018-0601-0826 item #15 alulminum composite panels | |
| Aug 7, 2019 | Completed final sign-off Feb 2020 | 1470 Owens St | Truebeck Construction | deferred submittal to pa 2018-0601-0826 item #10 security screen system | |
| Jul 2, 2019 | Completed final sign-off Mar 2020 | 1470 Owens St | Truebeck Construction | deferred submittal to pa 201806010826, item 2 "miscellaneous metal rails". metal rails | |
| Jul 2, 2019 | Completed final sign-off Mar 2020 | 1470 Owens St | Truebeck Construction | deferred submittal to pa 201806010826, item 3 "metal stud wall system" cold-formed steel framing | |
| Jul 2, 2019 | Completed final sign-off Mar 2020 | 1470 Owens St | Truebeck Construction | deferred submittal to pa 201806010826. aluminum fin facade. | |
| May 24, 2019 | Completed final sign-off Feb 2020 | 1470 Owens St | Truebeck Construction | installation of metal stairs associated with app#201806010826. n/a for maher | |
| Apr 23, 2019 | Completed final sign-off Jun 2020 | 1470 Owens St | Truebeck Construction | revision to 2018-1102-4884. revision include relocation of back flow preventer and revised fire department connection. | |
| Apr 19, 2019 | Completed final sign-off Feb 2020 | 1470 Owens St | Truebeck Construction | installation of curtain walls. deferred submittal to pa 201806010826 | |
| Apr 17, 2019 | Completed final sign-off Jun 2020 | 1470 Owens St | installation of cable barriers. ref 201806010826 for deferred submittal | $65,000 | |
| Apr 10, 2019 | Completed final sign-off Jun 2020 | 1470 Owens St | Truebeck Construction | rev to pa# 201806010826-s1 & s2 rev include fire pump room, configuration, security screen changes & landscape | |
| Feb 6, 2019 | Completed final sign-off Mar 2020 | 1470 Owens St | Truebeck Construction | production anger cast piles. | $900,000 |
| Jan 24, 2019 | Completed final sign-off Jun 2020 | 1470 Owens St | Truebeck Construction | revision to pa #201806010826-s1. scope includes: pile cap revisions, clarification of grade beam reinforcement, supplemental reinforcement, and other clarifications. | |
| Nov 6, 2018 | Completed final sign-off Oct 2020 | 1470 Owens St | Truebeck Construction | deferred plumbing permit for (n) bldg. for pid review only. related to pa# 2018-0601-0826. stormwater plan review. | |
| Nov 2, 2018 | Completed final sign-off Jun 2020 | 1470 Owens St | Truebeck Construction | 6" fire water service and sprinklers underground per nfpa 24. for sprinklers plan under 201806010826 addendum 3. there is existing 8' underground that will be removed under separate permit. | $10,369 |
| Oct 25, 2018 | Completed final sign-off Jun 2020 | 1470 Owens St | Truebeck Construction | design-build construction of auger cast piles load test & indicator pile program | $25,000 |
| Oct 17, 2018 | Completed final sign-off Feb 2020 | 1470 Owens St | Truebeck Construction | demolition of existing surface. grading in preparation of new parking lot per 201806010826 | |
| Jun 1, 2018 | Completed final sign-off Oct 2020 | 1470 Owens St | Truebeck Construction | erect a parking garage type 2b. | $6,000,000 |