Block 6657, lot 063
225 30th St
- City’s use
- Commercial Misc
- Built
- 1967
- Stories
- 3
- Building
- 41,656 sq ft
- Lot
- 23,959 sq ft
- Zoning
- RH2
- Construction type
- C
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
42 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Mar 26, 2026 | In progress issued May 2026 | 225 30th St | Diablo Telecom & Construction Inc | at&t: modification of an e unmanned telecommunications facility; r/r (3) antennas; r/r (3)rrus; r/r (1) power plant;r/r (1) battery cabinet with 4 rectifiers + 11 converts. install (7)new converters & 8 rectifiers in new battery cabinet. install 4 190 a battery, 1 bbu, 1 15amp and 650 amb dc breakDetails
at&t: modification of an e unmanned telecommunications facility; r/r (3) antennas; r/r (3)rrus; r/r (1) power plant;r/r (1) battery cabinet with 4 rectifiers + 11 converts. install (7)new converters & 8 rectifiers in new battery cabinet. install 4 190 a battery, 1 bbu, 1 15amp and 650 amb dc break | $81,850 |
| Nov 5, 2025 | Completed final sign-off Jan 2026 | 225 30th St | Ayoob & Peery Plumbing Co Inc | 1/f: add (3), relocate (2) fire sprinklers per t.i. ref permit 202503122127Details
1/f: add (3), relocate (2) fire sprinklers per t.i. ref permit 202503122127 | $3,106 |
| Oct 23, 2025 | Completed final sign-off Jan 2026 | 225 30th St | Rapid Fire Safety&Security Llc Dba Pafa | building permit: 202503132127. fire alarm only-tenant improvement, adding to existing notifier nfs640, 1 ceiling horn.Details
building permit: 202503132127. fire alarm only-tenant improvement, adding to existing notifier nfs640, 1 ceiling horn. | $7,500 |
| Mar 12, 2025 | Completed final sign-off Jan 2026 | 225 30th St | t. i. addition of prefabricated walk in freezer in existing storage space.Details
t. i. addition of prefabricated walk in freezer in existing storage space. | $25,000 | |
| Apr 26, 2022 | Completed final sign-off Nov 2022 | 225 30th St | Metropolitan Electrical Construction | att cell site mod: r/r 9 panel antennas.remove 6 rru's and replace with 3 new rrus. install 3 new diplexers near antennas sector.r/r 20 batteirs.install new rf safety signs and striping at rooftop.Details
att cell site mod: r/r 9 panel antennas.remove 6 rru's and replace with 3 new rrus. install 3 new diplexers near antennas sector.r/r 20 batteirs.install new rf safety signs and striping at rooftop. | $45,000 |
| Mar 17, 2022 | Completed final sign-off Jun 2022 | 225 30th St | Essa's Remodeling | revision to pa# 202009053608, title 24 exempt form.Details
revision to pa# 202009053608, title 24 exempt form. | |
| Oct 26, 2021 | Completed final sign-off Jun 2022 | 225 30th St | Pacific Auxiliary Fire Alarm | fire alarm ti adding 2 heat detectors, 2 monitor modueles and 2 relay modules for elevator upgrade. add 1 relay module, addressable and 1 relay conventional for fan and fsd control to existing notifier nfs-640 fire alarm systemDetails
fire alarm ti adding 2 heat detectors, 2 monitor modueles and 2 relay modules for elevator upgrade. add 1 relay module, addressable and 1 relay conventional for fan and fsd control to existing notifier nfs-640 fire alarm system | $16,292 |
| Sep 5, 2020 | Completed final sign-off Jun 2022 | 225 30th St | Essa's Remodeling | 1/f: repair existing elevator, machine room add 2 hour rating to the elevator machine room. in the storage and maintenance room. no sturctural changes, no changes to exterior facade. no change in useDetails
1/f: repair existing elevator, machine room add 2 hour rating to the elevator machine room. in the storage and maintenance room. no sturctural changes, no changes to exterior facade. no change in use | $70,000 |
| Jun 29, 2020 | Completed final sign-off Jun 2021 | 225 30th St | Essa's Remodeling | remodel serving area in room a210 and a230c. ada upgrade in restrooms.Details
remodel serving area in room a210 and a230c. ada upgrade in restrooms. | $450,000 |
| May 31, 2018 | Completed final sign-off Sep 2019 | 225 30th St | Metropolitan Electrical Construction | at&t swap 6 antennas, install 3 rrus, install 1 dc-12, swap 3 rrus, install 1 gps antenna, install 1 dc-6, 2 power trunks, install (1) 5216 & 1 vmuDetails
at&t swap 6 antennas, install 3 rrus, install 1 dc-12, swap 3 rrus, install 1 gps antenna, install 1 dc-6, 2 power trunks, install (1) 5216 & 1 vmu | $15,000 |
| Aug 17, 2017 | Never finaled issued Aug 2017, no final | 225 30th St | street spaceDetails
street space | ||
| Jun 16, 2017 | Completed final sign-off Oct 2017 | 225 30th St | att modification: r&r 3(e) rrus with 3 (n) rrus' install 3 (n) rrus and other small equipment. no antenna workDetails
att modification: r&r 3(e) rrus with 3 (n) rrus' install 3 (n) rrus and other small equipment. no antenna work | $20,000 | |
| May 11, 2017 | Never finaled issued May 2017, no final | 225 30th St | street space permitDetails
street space permit | ||
| Feb 15, 2017 | Completed final sign-off Oct 2018 | 225 30th St | Axis Construction | remove and replace 63 windows with new title 24 block frame double pane windows work is visible from the street all-weather 5000 series.Details
remove and replace 63 windows with new title 24 block frame double pane windows work is visible from the street all-weather 5000 series. | $420,000 |
| Oct 13, 2016 | Never finaled issued May 2017, no final | 225 30th St | street spaceDetails
street space | ||
| Mar 4, 2016 | Completed final sign-off Nov 2016 | 225 30th St | Metropolitan Electrical Construction | at&t, modification to (e) facility; remove and replace (3)(e) antennas with (3)(n) antennas (paint to match); install (3)(n) rrus-32; install (n) xmu inside (e) purcell;install (n) dc12 surge suppressor; install (n) 2" innerduct for fiber & dc power; extend (e) blinders at (n) antennas to 18" belowDetails
at&t, modification to (e) facility; remove and replace (3)(e) antennas with (3)(n) antennas (paint to match); install (3)(n) rrus-32; install (n) xmu inside (e) purcell;install (n) dc12 surge suppressor; install (n) 2" innerduct for fiber & dc power; extend (e) blinders at (n) antennas to 18" below | $18,000 |
| Sep 4, 2015 | Completed final sign-off Jan 2016 | 225 30th St | Broken Arrow Communications Inc | roof & ground: at&t mobility: modification to (e) att facility consisting of: installing (3)(n) rrus-11 units w/a2 modules; r&r (3)(e) antennas w/ (3)(n) antennas,paint to match; r&r dul unit (n) ous-41 unitDetails
roof & ground: at&t mobility: modification to (e) att facility consisting of: installing (3)(n) rrus-11 units w/a2 modules; r&r (3)(e) antennas w/ (3)(n) antennas,paint to match; r&r dul unit (n) ous-41 unit | $15,000 |
| Jan 29, 2015 | Completed final sign-off Mar 2015 | 225 30th St | Triton Tower Inc | at&t: revision to bp 201404254196; revised emf report on t-3 shows "yellow" striping and no barricades.Details
at&t: revision to bp 201404254196; revised emf report on t-3 shows "yellow" striping and no barricades. | |
| Nov 3, 2014 | Completed final sign-off Nov 2014 | 225 30th St | Buchanan General Contracting Co, Triton Tower Inc | revision to appl #2013.0509.6526 - to reflect install of 3 purcell cabinets original as shown 8 purcell cabinets. no change to rf report. at&t mobility macro wireless facility.Details
revision to appl #2013.0509.6526 - to reflect install of 3 purcell cabinets original as shown 8 purcell cabinets. no change to rf report. at&t mobility macro wireless facility. | |
| Apr 25, 2014 | Completed final sign-off Mar 2015 | 225 30th St | Triton Tower Inc | modification to an (e) unmanned at & t telecommunication facility consisting of removing & replacing 1 (e) dul with 1 new dus - 41 inside an (e) purcell cabinet & also adding 3 new rrus - 11 units with 3 new a-2 modules.Details
modification to an (e) unmanned at & t telecommunication facility consisting of removing & replacing 1 (e) dul with 1 new dus - 41 inside an (e) purcell cabinet & also adding 3 new rrus - 11 units with 3 new a-2 modules. | $10,000 |
| May 9, 2013 | Completed final sign-off Nov 2014 | 225 30th St | Buchanan General Contracting Co | at&t will be placing a new wireless communication facility on the building. including antenna and related equipment to enhance coverage to their network.Details
at&t will be placing a new wireless communication facility on the building. including antenna and related equipment to enhance coverage to their network. | $125,000 |
| Jan 13, 2011 | Completed final sign-off Dec 2011 | 225 30th St | Amone Corp | 3rd floor - remodel 3rd floor mens & womens toilet rooms, all work is barrier removal. provide 2 new drinking fountains on 3rd floor. upgrade reception counter on 3rd floor.Details
3rd floor - remodel 3rd floor mens & womens toilet rooms, all work is barrier removal. provide 2 new drinking fountains on 3rd floor. upgrade reception counter on 3rd floor. | $73,100 |
| May 28, 2010 | Never finaled issued May 2010, no final | 225 30th St | street space and mta parkingDetails
street space and mta parking | ||
| Aug 27, 2009 | Completed final sign-off Nov 2009 | 225 30th St | Pacific Auxiliary Fire Alarm | revision to existing system to remove two exterior manual alarms due to false alarms. revision to appl. #2006/1205/9130.Details
revision to existing system to remove two exterior manual alarms due to false alarms. revision to appl. #2006/1205/9130. | |
| Sep 23, 2008 | Never finaled issued Sep 2008, no final | 225 30th St | street space only.Details
street space only. | ||
| Sep 19, 2007 | Completed final sign-off Dec 2007 | 225 30th St | R L H Fire Protection Inc | add 1 sprinkler head to 2nd floor restroom.Details
add 1 sprinkler head to 2nd floor restroom. | $200 |
| Jun 29, 2007 | Completed final sign-off Dec 2007 | 225 30th St | revision to permit 200706143878 modification to door work at ground floor, add 1 door at dining roomDetails
revision to permit 200706143878 modification to door work at ground floor, add 1 door at dining room | $5,000 | |
| Jun 14, 2007 | Completed final sign-off Dec 2007 | 225 30th St | replace dinding room ceiling/lighting, replace lobby ceiling/lighting, sheetrock dining room & lobby, lobby door replacement, chain link fence, accessible toilet rooms at 2nd level, *building fully sprinklered any change in work under separate permit by contractor.Details
replace dinding room ceiling/lighting, replace lobby ceiling/lighting, sheetrock dining room & lobby, lobby door replacement, chain link fence, accessible toilet rooms at 2nd level, *building fully sprinklered any change in work under separate permit by contractor. | $190,000 | |
| Jan 19, 2007 | Expired or cancelled withdrawn Jul 2007 | 225 30th St | purpose of applciation:obtain change of occupancy from i1 to e-3. obtain certificate of occupancy as type e-3. application made at request of mocd/mod in order to maintain on lok funding grant eligibity at above site. no construction shall be completed as part of this application. ref. info.attachedDetails
purpose of applciation:obtain change of occupancy from i1 to e-3. obtain certificate of occupancy as type e-3. application made at request of mocd/mod in order to maintain on lok funding grant eligibity at above site. no construction shall be completed as part of this application. ref. info.attached | ||
| Dec 5, 2006 | Never finaled issued Dec 2006, no final | 225 30th St | Pacific Auxiliary Fire Alarm | as builts to pa# 2006/10/10/4549. relocation of the notification appliances.Details
as builts to pa# 2006/10/10/4549. relocation of the notification appliances. | $1,000 |
| Oct 10, 2006 | Never finaled issued Oct 2006, no final | 225 30th St | Pacific Auxiliary Fire Alarm | installation of a new fire alarm system (whole building).Details
installation of a new fire alarm system (whole building). | $50,000 |
| Sep 20, 2006 | Completed final sign-off Nov 2006 | 225 30th St | Atlas Heating & Vent Co | replace 2 air handlers with 2 air conditioning units, install new return air duct, replace roof exhaust fansDetails
replace 2 air handlers with 2 air conditioning units, install new return air duct, replace roof exhaust fans | $65,800 |
| Apr 28, 2006 | Completed final sign-off May 2007 | 225 30th St | Hoi's Construction | renew 200512099959, 20040914059, 200501284198 for final inspectionDetails
renew 200512099959, 20040914059, 200501284198 for final inspection | $50,000 |
| Mar 17, 2006 | Never finaled issued Mar 2006, no final | 225 30th St | Pacific Auxiliary Fire Alarm | addition to existing fire alarm system due to remodel on 1st floorDetails
addition to existing fire alarm system due to remodel on 1st floor | $12,000 |
| Dec 9, 2005 | Expired or cancelled expired Jun 2007 | 225 30th St | Hoi's Construction | rev.appl#200409144059 change life foyer to conform to field conditions.Details
rev.appl#200409144059 change life foyer to conform to field conditions. | |
| Jan 28, 2005 | Expired or cancelled expired Jun 2007 | 225 30th St | single privacy unisex toilet rm at 1st flr level, including demolition, partitions, plumbing & elecDetails
single privacy unisex toilet rm at 1st flr level, including demolition, partitions, plumbing & elec | $10,000 | |
| Sep 14, 2004 | Expired or cancelled expired Jun 2007 | 225 30th St | barrier removal project path of travel from street/public toilets work includesDetails
barrier removal project path of travel from street/public toilets work includes | $95,625 | |
| May 14, 2003 | Completed final sign-off Jul 2003 | 225 30th St | Pacific Auxiliary Fire Alarm | upgrade/expand (e)fire alarm control panel to accomdate duct detectors added during remodel.as builtDetails
upgrade/expand (e)fire alarm control panel to accomdate duct detectors added during remodel.as built | $4,000 |
| Mar 4, 2003 | Completed final sign-off Jul 2003 | 225 30th St | San Francisco Fire Protection | fire suppression system installation on hood and duct on ground floorDetails
fire suppression system installation on hood and duct on ground floor | $2,500 |
| Feb 7, 2003 | Completed final sign-off Jul 2003 | 225 30th St | Pacific Automatic Sprinkler | for fire sprinkler work only, cap off 1, relocate 9 & add 4 fire sprinklers to properly protect theDetails
for fire sprinkler work only, cap off 1, relocate 9 & add 4 fire sprinklers to properly protect the | $4,200 |
| Aug 26, 2002 | Never finaled issued Aug 2002, no final | 225 30th St | sidewalkDetails
sidewalk | ||
| Apr 3, 2002 | Completed final sign-off Jul 2003 | 225 30th St | mechanical system upgrade work only. replace grease hood and roof ex fan, new supply air systemDetails
mechanical system upgrade work only. replace grease hood and roof ex fan, new supply air system | $90,000 |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Pacific Auxiliary Fire Alarm (6), Essa's Remodeling (3), Metropolitan Electrical Construction (3), Triton Tower Inc (3), Buchanan General Contracting Co (2), Hoi's Construction (2), Amone Corp, Atlas Heating & Vent Co, Axis Construction, Ayoob & Peery Plumbing Co Inc, Broken Arrow Communications Inc, Diablo Telecom & Construction Inc, Pacific Automatic Sprinkler, R L H Fire Protection Inc, Rapid Fire Safety&Security Llc Dba Pafa, San Francisco Fire Protection
- Architects
- Dennis Singer (4), Dahlin Group Inc, Julian White
- Engineers
- James Spore (4), Andrew Haldane, James Spore, Joseph J Fitzsimons, Julian White, Matthew J. Freedman, Seung Kun Oh, Tomislav Gajic
- Designers
- Ayoob & Peery Plumbing