Block 5869, lot 013
4175 Mission St
- City’s use
- Commercial Retail
- Built
- 1963
- Stories
- 2
- Units
- 1
- Rooms
- 2 bathrooms
- Building
- 24,284 sq ft
- Lot
- 42,688 sq ft
- Zoning
- RH1
- Construction type
- D
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
23 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| May 4, 2026 | In progress filed May 2026, not yet issued | 4175 Mission St | relocate (2) antennas and (6) rrus in sector c from cupola facade to (n) pole mount on roof. replace (3) (e)rrus with (3)(n) rrus. install (4) (n) antennas. replace (3)(e) nema boxes with (1) (n) nema box, (1)(e) fiber trunk with (1)(n) fiber trunk and (6) (e) power trunks with (3)(n) power trunks.Details
relocate (2) antennas and (6) rrus in sector c from cupola facade to (n) pole mount on roof. replace (3) (e)rrus with (3)(n) rrus. install (4) (n) antennas. replace (3)(e) nema boxes with (1) (n) nema box, (1)(e) fiber trunk with (1)(n) fiber trunk and (6) (e) power trunks with (3)(n) power trunks. | $80,000 | |
| Jan 26, 2023 | Completed final sign-off Nov 2023 | 4175 Mission St | Metropolitan Electrical Construction | revison to bpa#202203250944, replace (e) antenna mountsDetails
revison to bpa#202203250944, replace (e) antenna mounts | $10,000 |
| Mar 25, 2022 | Completed final sign-off Nov 2023 | 4175 Mission St | Ericsson Inc Dba E U S Inc | mod (e) at&t site: remove 9 (e) antennas, install 5 new antennas. install 1 new baseband 6648 in (e) rack. install 1 new string of batteries (marathon m12v180ft) 180att.Details
mod (e) at&t site: remove 9 (e) antennas, install 5 new antennas. install 1 new baseband 6648 in (e) rack. install 1 new string of batteries (marathon m12v180ft) 180att. | $25,000 |
| Jan 27, 2022 | Never finaled filed Jan 2022, never issued | 4175 Mission St | Discount Plumbing Co | storm drain replacement/ repair trenchless method in back of building comply with pid 202286686Details
storm drain replacement/ repair trenchless method in back of building comply with pid 202286686 | $20,000 |
| Oct 24, 2020 | Completed final sign-off Mar 2021 | 4175 Mission St | Metropolitan Electrical Construction, Ericsson Inc Dba E U S Inc | at&t modification: swap (9) antennas, paint to match. remove (9) existing rrus. install 12 new rrus, install (n) battery rack.Details
at&t modification: swap (9) antennas, paint to match. remove (9) existing rrus. install 12 new rrus, install (n) battery rack. | $42,000 |
| Jul 3, 2018 | Expired or cancelled cancelled Jan 2026 | 4175 Mission St | rooftop: cell site mod: swap 9 antennaes, install 3 dc06, install 1 fiber & 2dc trunks, install 9 rru's, remove 6 rru's, install 1-5216, update electrical to 200a, install meter, run a/c wiring.n/a for maherDetails
rooftop: cell site mod: swap 9 antennaes, install 3 dc06, install 1 fiber & 2dc trunks, install 9 rru's, remove 6 rru's, install 1-5216, update electrical to 200a, install meter, run a/c wiring.n/a for maher | $25,000 | |
| Mar 30, 2017 | Completed final sign-off Feb 2018 | 4175 Mission St | Shah & Associates Inc Dba P D C Corporat | att modification: r&r 3 extg antennas with 3 new antennas, install 6nw tmha, 3 new rrus-e2, 3 new rrus-11, remove 2 extg cabinets, extg equip rack, 6 dtmas, r&r extg 2 dus41 with new dus5216 & nw xmu. paint antennas, cables to match. n/a for maherDetails
att modification: r&r 3 extg antennas with 3 new antennas, install 6nw tmha, 3 new rrus-e2, 3 new rrus-11, remove 2 extg cabinets, extg equip rack, 6 dtmas, r&r extg 2 dus41 with new dus5216 & nw xmu. paint antennas, cables to match. n/a for maher | $31,000 |
| Feb 29, 2016 | Completed final sign-off Nov 2016 | 4175 Mission St | Slc Inc | att: modification to at&t facility: r&r 6(e) at&t antennas w/6(n) antennas. r&r 3(e) rruw units w/3new rrus. install 3 new rrus-11 units w/3 new a2 modules. install new dus-41 unit & new xmu unit w/i new 6601 chassis inside (e) rack. reloacte (e) dus41 unit w/i 6601 chassis (e) 19" rack. mahernaDetails
att: modification to at&t facility: r&r 6(e) at&t antennas w/6(n) antennas. r&r 3(e) rruw units w/3new rrus. install 3 new rrus-11 units w/3 new a2 modules. install new dus-41 unit & new xmu unit w/i new 6601 chassis inside (e) rack. reloacte (e) dus41 unit w/i 6601 chassis (e) 19" rack. maherna | $24,000 |
| Nov 22, 2013 | Never finaled issued Dec 2013, no final | 4175 Mission St | A-1 Fence & Decks Co. | building the fence around the waste containers (two locations)Details
building the fence around the waste containers (two locations) | $3,500 |
| Oct 15, 2013 | Completed final sign-off Dec 2014 | 4175 Mission St | Electric Tech Construction Inc | modification to existing att unmanned telecommunication facility consisting of adding 3 new rrvs-11's. running new fiber/edc power from existing equipment room through existing rooftop doghouse and existing cable trays. no change to antennas, no other workDetails
modification to existing att unmanned telecommunication facility consisting of adding 3 new rrvs-11's. running new fiber/edc power from existing equipment room through existing rooftop doghouse and existing cable trays. no change to antennas, no other work | $6,000 |
| Feb 24, 2011 | Completed final sign-off Feb 2012 | 4175 Mission St | Pinnacle Wireless Usa Inc. | remove & replace (3) antennas, relocate antennas in sec a & c, add (6) rru's, new splice bos, (3) surge suppressors, add new gps antenna, add new 6601 cabient into (e) 19' zack & add new innerducts.Details
remove & replace (3) antennas, relocate antennas in sec a & c, add (6) rru's, new splice bos, (3) surge suppressors, add new gps antenna, add new 6601 cabient into (e) 19' zack & add new innerducts. | $35,000 |
| Mar 12, 2010 | Completed final sign-off Apr 2011 | 4175 Mission St | Pinnacle Wireless Usa Inc. | modification to an (e) unmanned telecommumincation facility consisting of removing (e) toma equipment & adding 1 new 3206 rbs cabinet in (e) equipment rm, also installing 6 new coax cables from the (e) equipment rm to antenna;s & adding a new rofftop doghouse, new 12" cable tray, also remove/repl 12Details
modification to an (e) unmanned telecommumincation facility consisting of removing (e) toma equipment & adding 1 new 3206 rbs cabinet in (e) equipment rm, also installing 6 new coax cables from the (e) equipment rm to antenna;s & adding a new rofftop doghouse, new 12" cable tray, also remove/repl 12 | $25,000 |
| Jan 7, 2009 | Completed final sign-off Dec 2009 | 4175 Mission St | Capital Tower & Communications | at&t proposes to modify an extg telecommunications site. the modification to the facility will consist:the replacement of 3 extg antennas with 3 smaller antennas and installation of 6 new coax cables from the extg equipment room to the new antennas.Details
at&t proposes to modify an extg telecommunications site. the modification to the facility will consist:the replacement of 3 extg antennas with 3 smaller antennas and installation of 6 new coax cables from the extg equipment room to the new antennas. | $5,000 |
| Oct 10, 2006 | Never finaled issued Oct 2006, no final | 4175 Mission St | San Francisco Fire Protection | add communicator for water flow monitoring.Details
add communicator for water flow monitoring. | $1,000 |
| Sep 25, 2006 | Completed final sign-off Oct 2006 | 4175 Mission St | S M I Construction Inc. | revision to pa 200606234852, wall details revision.Details
revision to pa 200606234852, wall details revision. | |
| Sep 19, 2006 | Completed final sign-off Oct 2006 | 4175 Mission St | Ok Fire System | install a fire system in a kitchen hoodDetails
install a fire system in a kitchen hood | $2,800 |
| Aug 25, 2006 | Completed final sign-off Oct 2006 | 4175 Mission St | Success Sign Inc. ***See Note********* | 1 set of internal illuminated channel letter.Details
1 set of internal illuminated channel letter. | |
| Aug 25, 2006 | Completed final sign-off Oct 2006 | 4175 Mission St | Success Sign Inc. ***See Note********* | 1 set of internal illuminated channel letter.Details
1 set of internal illuminated channel letter. | |
| Aug 25, 2006 | Never finaled issued Aug 2006, no final | 4175 Mission St | Success Sign Inc. ***See Note********* | existing post sign. replace double face only.Details
existing post sign. replace double face only. | |
| Jul 20, 2006 | Completed final sign-off Oct 2006 | 4175 Mission St | All Purpose Fire Protection | lower 4 sprinklers for new bathrooms at 1st floor.Details
lower 4 sprinklers for new bathrooms at 1st floor. | $1,000 |
| Jun 23, 2006 | Completed final sign-off Oct 2006 | 4175 Mission St | S M I Construction Inc. | revision to pa 200604219603Details
revision to pa 200604219603 | |
| Apr 21, 2006 | Completed final sign-off Oct 2006 | 4175 Mission St | S M I Construction Inc. | add accessible bathrooms, total two, replace some refrigeration units. change "cala food" into "manila orientkl market"Details
add accessible bathrooms, total two, replace some refrigeration units. change "cala food" into "manila orientkl market" | $70,000 |
| Dec 2, 2002 | Never finaled issued Dec 2002, no final | 4175 Mission St | sidewalk repairDetails
sidewalk repair |
Find contractors for work like this