Block 3973, lot 002A
450 Potrero Ave
- City’s use
- Industrial
- Built
- 1919
- Stories
- 1
- Units
- 1
- Rooms
- 2 bathrooms
- Building
- 5,000 sq ft
- Lot
- 5,000 sq ft
- Zoning
- M1
- Construction type
- C
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
6 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Dec 14, 2018 | Never finaled issued Dec 2018, no final | 450 Potrero Av | S F Crown Roofing | re-roofingDetails
re-roofing | $38,880 |
| Jul 2, 2015 | Never finaled issued Jul 2015, no final | 450 Potrero Av | Discount Signs & Neon Inc | to erect one illuminated wall sign 20 sq feet. n/a for maherDetails
to erect one illuminated wall sign 20 sq feet. n/a for maher | $3,000 |
| Jul 21, 2011 | Never finaled issued Jul 2011, no final | 450 Potrero Av | to obtain final inspection for work approved under pa #200901270852. all work is complete.Details
to obtain final inspection for work approved under pa #200901270852. all work is complete. | ||
| Sep 17, 2009 | Never finaled issued Sep 2009, no final | 450 Potrero Av | Performance Systems Co | proposed fire suppression system for one pre-fab spray booth & paint mixing room.Details
proposed fire suppression system for one pre-fab spray booth & paint mixing room. | $4,500 |
| Aug 19, 2009 | Expired or cancelled cancelled Jan 2026 | 450 Potrero Av | replace 1 existing paint existing booth for 1 new spray boothDetails
replace 1 existing paint existing booth for 1 new spray booth | $35,000 | |
| Jan 27, 2009 | Never finaled issued Feb 2009, no final | 450 Potrero Av | Air Filtration Co. Inc. | replace existing spray paint with new auto paint spray booth with heated air make-up system, duct 6' above roof line. also add (1) paint mix room. correct 1 restroom door swing. fire suppression by licensed contractor, not afc.Details
replace existing spray paint with new auto paint spray booth with heated air make-up system, duct 6' above roof line. also add (1) paint mix room. correct 1 restroom door swing. fire suppression by licensed contractor, not afc. | $116,273 |
Find contractors for work like this