Block 3786, lot 018
85 Bluxome St
- City’s use
- Commercial Office
- Built
- 2016
- Stories
- 5
- Building
- 56,845 sq ft
- Lot
- 11,000 sq ft
- Zoning
- MUO
- Construction type
- NA
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
28 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jun 11, 2021 | Completed final sign-off Aug 2021 | 85 Bluxome St | Anderson, Rowe & Buckley, Inc. | existing fire sprinkler system - tenant improvements relocated 8 sprinklersDetails
existing fire sprinkler system - tenant improvements relocated 8 sprinklers | $1,688 |
| May 10, 2021 | Completed final sign-off Apr 2022 | 85 Bluxome St | Skyline Construction | ti on the 2nd fl to create two new shared offices. mechanical & electrical included.Details
ti on the 2nd fl to create two new shared offices. mechanical & electrical included. | $150,000 |
| Apr 29, 2021 | Expired or cancelled cancelled Jan 2025 | 85 Bluxome St | Pyro-Comm Systems, Inc. | voluntary modify existing fire alarm system; add/remove devices.Details
voluntary modify existing fire alarm system; add/remove devices. | $1,500 |
| Feb 25, 2020 | Never finaled issued Feb 2020, no final | 85 Bluxome St | street spaceDetails
street space | ||
| Nov 18, 2019 | Never finaled issued Nov 2019, no final | 85 Bluxome St | street space w/ sfmta metersDetails
street space w/ sfmta meters | ||
| Oct 6, 2016 | Never finaled issued Oct 2016, no final | 85 Bluxome St | street space permitDetails
street space permit | ||
| Sep 9, 2016 | Completed final sign-off Sep 2016 | 85 Bluxome St | Bcci Construction Company | (e) plans for sffd place of assembly permitDetails
(e) plans for sffd place of assembly permit | |
| Aug 9, 2016 | Completed final sign-off Dec 2016 | 85 Bluxome St | Bcci Construction Company | work associated with approved pa 2016-0525-7386 for the addition of room terrace paver system, planters & benchesDetails
work associated with approved pa 2016-0525-7386 for the addition of room terrace paver system, planters & benches | $15,500 |
| Aug 4, 2016 | Completed final sign-off Sep 2016 | 85 Bluxome St | Anderson, Rowe & Buckley, Inc. | entire bldg fire sprinkler system for tenant improvement - 22 relocated, 11 added, & 6 removed sprinklers. ref #201404072588. n/a maher ordinanceDetails
entire bldg fire sprinkler system for tenant improvement - 22 relocated, 11 added, & 6 removed sprinklers. ref #201404072588. n/a maher ordinance | $16,500 |
| Jul 6, 2016 | Completed final sign-off Dec 2016 | 85 Bluxome St | mech revisions to approved pa mech/elec 201605187792 in response to sffd comments to include a sequence of operation on the mechanical drawings for new fsd's. ref arch ti 201605177688 to amend the occupancy to include assembly use on ground floor.Details
mech revisions to approved pa mech/elec 201605187792 in response to sffd comments to include a sequence of operation on the mechanical drawings for new fsd's. ref arch ti 201605177688 to amend the occupancy to include assembly use on ground floor. | ||
| Jun 10, 2016 | Never finaled issued Aug 2016, no final | 85 Bluxome St | Pyro-Comm Systems, Inc. | new fire alarm devices added to tenant improvement in an (e)bldg to include 1 power supply,3 sd,49relay modules,1 voltage relay,2 dual monitor modules 48 duct detectors,18 strobes 57 horn/strobes,ref. 201605177688(1st flr)201605258391 (2,3,4thflr)201605258386(5th & roof); maher n/aDetails
new fire alarm devices added to tenant improvement in an (e)bldg to include 1 power supply,3 sd,49relay modules,1 voltage relay,2 dual monitor modules 48 duct detectors,18 strobes 57 horn/strobes,ref. 201605177688(1st flr)201605258391 (2,3,4thflr)201605258386(5th & roof); maher n/a | $57,000 |
| May 25, 2016 | Completed final sign-off Dec 2016 | 85 Bluxome St | Bcci Construction Company | ti on the 5th floor & roof including minor demo, construction of non-structural partitions, doors, mill work ceilings & finishes & associated mep. fire life safety under separate permit. maher naDetails
ti on the 5th floor & roof including minor demo, construction of non-structural partitions, doors, mill work ceilings & finishes & associated mep. fire life safety under separate permit. maher na | $1,225,000 |
| May 25, 2016 | Completed final sign-off Dec 2016 | 85 Bluxome St | Bcci Construction Company | tenat improvement on the 2nd, 3rd and 4th floors including minor demo. construction of non structural partitions, doors, millwork, ceilings and associated mep. fire life safety under separate permit. maher naDetails
tenat improvement on the 2nd, 3rd and 4th floors including minor demo. construction of non structural partitions, doors, millwork, ceilings and associated mep. fire life safety under separate permit. maher na | $2,850,000 |
| May 18, 2016 | Completed final sign-off Dec 2016 | 85 Bluxome St | Bcci Construction Company | ist floor: mep associated with approved #2016-0517-7688. works including new coils, exhaust fan, ductwork & lighting.Details
ist floor: mep associated with approved #2016-0517-7688. works including new coils, exhaust fan, ductwork & lighting. | $512,000 |
| May 17, 2016 | Completed final sign-off Dec 2016 | 85 Bluxome St | Bcci Construction Company | 1st floor tenant improvement including demolition of interior non-structural partitions & build back of new partitions, doors, millwork & ceilings. mep & l/s under separate permit. ref pa #201404072588 site permit office bldg only. n/a maher ordinanceDetails
1st floor tenant improvement including demolition of interior non-structural partitions & build back of new partitions, doors, millwork & ceilings. mep & l/s under separate permit. ref pa #201404072588 site permit office bldg only. n/a maher ordinance | $389,000 |
| May 17, 2016 | Completed final sign-off Sep 2016 | 85 Bluxome St | Bcci Construction Company | installation of emergency generator to the roof, piping details, associated structural, mechanical and electrical. n/a for maherDetails
installation of emergency generator to the roof, piping details, associated structural, mechanical and electrical. n/a for maher | $750,000 |
| Mar 31, 2016 | Completed final sign-off Sep 2016 | 85 Bluxome St | Bcci Construction Company | puc to install new 6-inch fire service up to street curb off of 8-inch main on bluxome. c-16 to connect to that new fire service with 6-inch underground that goes for curb into bldg under appl # 2014/04/07/2588-s-4Details
puc to install new 6-inch fire service up to street curb off of 8-inch main on bluxome. c-16 to connect to that new fire service with 6-inch underground that goes for curb into bldg under appl # 2014/04/07/2588-s-4 | |
| Feb 22, 2016 | Never finaled issued Feb 2016, no final | 85 Bluxome St | street spaceDetails
street space | ||
| Sep 25, 2015 | Completed final sign-off Dec 2016 | 85 Bluxome St | Bcci Construction Company | revision to approved pa# 2014/04/07/2588 s-2. to relocate pg & e voult. ** maher: compliance with ordinance no# 155-13 not required **Details
revision to approved pa# 2014/04/07/2588 s-2. to relocate pg & e voult. ** maher: compliance with ordinance no# 155-13 not required ** | |
| Aug 10, 2015 | Never finaled issued Aug 2015, no final | 85 Bluxome St | street space & mta.Details
street space & mta. | ||
| Jul 9, 2015 | Completed final sign-off Dec 2016 | 85 Bluxome St | Bcci Construction Company | installation of 27 windows at property line associated with 201404072588. t24 under separate permit maher not reqDetails
installation of 27 windows at property line associated with 201404072588. t24 under separate permit maher not req | $9,500 |
| May 19, 2015 | Completed final sign-off May 2016 | 85 Bluxome St | Pyro-Comm Systems, Inc. | new fire alarm for entire bld: 1 facu. 1 power supply. 1 annunciator. 22 modules. 1 pull station. 15 smoke detectors. 3 heat detectors. 19 duct detectors. 21 horn/strobes. 11 strobes. ref pa 2014 0407 2588Details
new fire alarm for entire bld: 1 facu. 1 power supply. 1 annunciator. 22 modules. 1 pull station. 15 smoke detectors. 3 heat detectors. 19 duct detectors. 21 horn/strobes. 11 strobes. ref pa 2014 0407 2588 | $24,300 |
| Jan 27, 2015 | Never finaled issued Jan 2015, no final | 85 Bluxome St | street spaceDetails
street space | ||
| Jan 8, 2015 | Completed final sign-off Sep 2016 | 85 Bluxome St | Ayoob & Peery Plumbing Co Inc | install underground pipe from existing 6" fire service underground to flange above floor slab. ref. appl. 2014.0407.2588.Details
install underground pipe from existing 6" fire service underground to flange above floor slab. ref. appl. 2014.0407.2588. | $5,000 |
| Nov 4, 2014 | Never finaled issued Nov 2014, no final | 85 Bluxome St | street space and mta parkingDetails
street space and mta parking | ||
| May 7, 2014 | Completed final sign-off Dec 2016 | 85 Bluxome St | Bcci Construction Company | demo a commercial building.(compliance with mahner ordinance no.155-13 required)Details
demo a commercial building.(compliance with mahner ordinance no.155-13 required) | $250,000 |
| Apr 7, 2014 | Completed final sign-off Dec 2016 | 85 Bluxome St | Bcci Construction Company | to erect 5 stories of office building - compliance with maher ordinance no.155-13 required route to healthDetails
to erect 5 stories of office building - compliance with maher ordinance no.155-13 required route to health | $12,000,000 |
| Nov 15, 2000 | Expired or cancelled cancelled Dec 2002 | 83 Bluxome St | remodel & refurbish all 3 floors, upgrade bathrms to ada compliance. add two new exit stairs. mechanDetails
remodel & refurbish all 3 floors, upgrade bathrms to ada compliance. add two new exit stairs. mechan | $650,000 |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Bcci Construction Company (12), Pyro-Comm Systems, Inc. (3), Anderson, Rowe & Buckley, Inc. (2), Ayoob & Peery Plumbing Co Inc, Skyline Construction
- Architects
- Clement Soga Insiter Design (3), Larry Grondahl, Michelle Jones
- Engineers
- Alexander Joseph Pacheco, Kevin Carter, Ronald Migdal, Rudolfo P Bustos Iii
- Designers
- Clement Soga