Permits filed here
6 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| May 4, 2023 | Completed final sign-off Sep 2023 | 301 Mission St | Aaron Gordon Construction Inc | unit 54a: revision to bpa#202302061414 to remove plumbing from scopeDetails
unit 54a: revision to bpa#202302061414 to remove plumbing from scope | |
| Feb 28, 2023 | Completed final sign-off Mar 2023 | 301 Mission St | Allied Fire Protection | unit 54a: change (e)hsw sprinkler to concealed style vk490. relocate (4)(e)concealed vk462 sprinklers. relocate (5)(e) hsw sprinkler. add (1) concealed vk462 in new closet. delete (1)(e) concealed vk462 due to new soffit living/dining rm agl-gc 202302061414Details
unit 54a: change (e)hsw sprinkler to concealed style vk490. relocate (4)(e)concealed vk462 sprinklers. relocate (5)(e) hsw sprinkler. add (1) concealed vk462 in new closet. delete (1)(e) concealed vk462 due to new soffit living/dining rm agl-gc 202302061414 | $6,500 |
| Feb 6, 2023 | Completed final sign-off Sep 2023 | 301 Mission St | Aaron Gordon Construction Inc | unit # 54a: remodel of e aprtment, including new light fixtures, new lighting control, new window shades, new flooring, new bath tub, new ceiling soffit, and new cabinetry.Details
unit # 54a: remodel of e aprtment, including new light fixtures, new lighting control, new window shades, new flooring, new bath tub, new ceiling soffit, and new cabinetry. | $300,000 |
| Aug 23, 2012 | Completed final sign-off Aug 2012 | 301 Mission St | Garibaldi Plumbing Company Inc | #54a - relcoate (2) existing fire sprinkler heads, add (1) to accomodate new design.Details
#54a - relcoate (2) existing fire sprinkler heads, add (1) to accomodate new design. | $1,000 |
| Aug 2, 2012 | Never finaled issued Aug 2012, no final | 301 Mission St | add address 301 miision st#54a as block#3719 lot#364Details
add address 301 miision st#54a as block#3719 lot#364 | ||
| Aug 2, 2012 | Completed final sign-off Jan 2013 | 301 Mission St | Black Mountain Development | open wall between living room and study for pass thru access. remove wall at dining rm and kitchen. replace countertop. add recessed lights in soffit over counter. move existing switches to adjoining walls. repaint as needed. field verify fa/sprinkler/co alarm coverage.swi 8/2/11.Details
open wall between living room and study for pass thru access. remove wall at dining rm and kitchen. replace countertop. add recessed lights in soffit over counter. move existing switches to adjoining walls. repaint as needed. field verify fa/sprinkler/co alarm coverage.swi 8/2/11. | $42,500 |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Aaron Gordon Construction Inc (2), Allied Fire Protection, Black Mountain Development, Garibaldi Plumbing Company Inc
- Architects
- Matthew Ininns
- Authorized agent-otherss
- William Murphy
- Designers
- Matthew Ininns
Find contractors for work like this
Starts from the last permit filed here; change it to describe your own project. Results cover apartment buildings like this one.