Block 2918, lot 031
110 Hernandez Av
8 permits filed for this property since 2000.
CompletedIn progressNever finaledExpired or cancelled
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jan 2, 2025 | Completed | 110 Hernandez Av | Roofing Logistics | remove and replace 80 sq ft of stucco between roofs. (not street visible) | $1,800 |
| Jan 2, 2025 | Completed | 110 Hernandez Av | Roofing Logistics | reroofing (no hot works) | $38,000 |
| Oct 24, 2024 | In progress | 110 Hernandez Av | Gilman Screens And Kitchens | repair of stucco west elevation and north elevation approx. 1600 sq ft. like for like. | $5,000 |
| Jul 26, 2024 | In progress | 110 Hernandez Av | Gilman Screens And Kitchens | window revision to center at the above pa#202103116419. windows should be fiberglass | $2,000 |
| Feb 29, 2024 | In progress | 110 Hernandez Av | Gilman Screens And Kitchens | rev to 2021-0311-6419; remove (e) garage slab at area of new adu for a new conc slab | $32,000 |
| Mar 11, 2021 | Never finaled | 110 Hernandez Av | Gilman Screens And Kitchens | remodel master bath. reconfigure (e) 2-car garage & lower level to 1-car garage with in-law bedroom, kitchen & bathroom. window to become door/(n) window @ kitchen, add (n) window/change 2-car garage door to single (state adu program) | $300,000 |
| May 9, 2011 | Completed | 110 Hernandez Av | Excelsior Roofing Company | reroofing | $13,450 |
| Oct 1, 2009 | Completed | 110 Hernandez Av | American Home Renewal Inc | replace (14) windows with vinyl, like for like no framing being removed. u-factor 0.67 max. no structural work. | $15,200 |