Block 1249, lot 024
730 Stanyan St
- City’s use
- Government
- Built
- 1975
- Stories
- 1
- Units
- 1
- Rooms
- 2 bathrooms
- Building
- 3,476 sq ft
- Lot
- 37,813 sq ft
- Zoning
- HAIGHT
- Construction type
- D
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
19 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Oct 3, 2025 | Completed final sign-off Nov 2025 | 730 Stanyan St | Cahill Contractors Llc. | to obtain final inspection for work approved under pa 202308214844. all work is complete.Details
to obtain final inspection for work approved under pa 202308214844. all work is complete. | |
| May 20, 2025 | Completed final sign-off Dec 2025 | 730 Stanyan St | Cahill Contractors Llc. | revision to pa# 202103317637- s3, amendment to reflect actual elevator hoistway dimension a6.03.Details
revision to pa# 202103317637- s3, amendment to reflect actual elevator hoistway dimension a6.03. | |
| Mar 21, 2025 | In progress issued Apr 2025 | 730 Stanyan St | Garnett Signs Llc | evacuation maps (23) level 1-8Details
evacuation maps (23) level 1-8 | $5,750 |
| Dec 3, 2024 | Completed final sign-off Oct 2025 | 730 Stanyan St | Cahill Hercules Buildeers Joint Venture, Rcm Fire Protection Inc. | revision to previously 20210331737 fire only revision: per sffd request: remove sprinkler in elevator control room levelDetails
revision to previously 20210331737 fire only revision: per sffd request: remove sprinkler in elevator control room level | $500 |
| Dec 2, 2024 | Completed final sign-off Dec 2025 | 730 Stanyan St | Cahill Hercules Buildeers Joint Venture | revision to 202103317637- to provide sffd release at ground floor reception desk. add elevator plans showing smoke detector location at hoistway top and access panel. provide elvator manf letter.remove sprikler in elevator control room l.8.Details
revision to 202103317637- to provide sffd release at ground floor reception desk. add elevator plans showing smoke detector location at hoistway top and access panel. provide elvator manf letter.remove sprikler in elevator control room l.8. | $5,000 |
| Jul 22, 2024 | In progress issued Jul 2024 | 700 Stanyan St | per pa #202103317637, add commercial addresses to apn 1249/024, 1780, 1790 waller st, and 1865, 1895 haight st.Details
per pa #202103317637, add commercial addresses to apn 1249/024, 1780, 1790 waller st, and 1865, 1895 haight st. | ||
| Jul 22, 2024 | In progress issued Jul 2024 | 1780 Waller St | per pa #202103317637, add commercial addresses to apn 1249/024, 1780, 1790 waller st, and 1865, 1895 haight st.Details
per pa #202103317637, add commercial addresses to apn 1249/024, 1780, 1790 waller st, and 1865, 1895 haight st. | ||
| Aug 21, 2023 | Expired or cancelled expired Dec 2025 | 730 Stanyan St | Cahill Hercules Buildeers Joint Venture | revision to pa 202305047102 temporary shoring system. construction set soldier beam & soil mixed wall w/ wood lagging to retain cuts up to 11.5 feet below (e) site grade. 23mse-00253 issued under original permit. reduction in original scope of work.Details
revision to pa 202305047102 temporary shoring system. construction set soldier beam & soil mixed wall w/ wood lagging to retain cuts up to 11.5 feet below (e) site grade. 23mse-00253 issued under original permit. reduction in original scope of work. | $2,500 |
| May 4, 2023 | Completed final sign-off Nov 2025 | 730 Stanyan St | Cahill Hercules Buildeers Joint Venture | temporary shoring for use to construct 100% affordable housing project related to permit application number 202103317637-s.Details
temporary shoring for use to construct 100% affordable housing project related to permit application number 202103317637-s. | $622,580 |
| Dec 29, 2022 | In progress issued Feb 2026 | 730 Stanyan St | Cahill Contractors Llc. | ground flr: ti for use of early childcare & education center. consists of non-structural partitions & finishes, exterior courtyard imrpovements, mep low voltage & fire protection systems will be design build and submitted under separate permits. fixtures & plumbing are shown on plans for ref only.Details
ground flr: ti for use of early childcare & education center. consists of non-structural partitions & finishes, exterior courtyard imrpovements, mep low voltage & fire protection systems will be design build and submitted under separate permits. fixtures & plumbing are shown on plans for ref only. | $481,612 |
| Mar 31, 2021 | Completed final sign-off Nov 2025 | 730 Stanyan St | Cahill Contractors Llc., Cahill Hercules Buildeers Joint Venture | new 8-story building containing 175,426 square feet of residential uses above 12,556 square feet of ground floor commercial uses on vacant lot. the project will provide 160 100% affordable housing rental units.Details
new 8-story building containing 175,426 square feet of residential uses above 12,556 square feet of ground floor commercial uses on vacant lot. the project will provide 160 100% affordable housing rental units. | $60,000,000 |
| May 21, 2019 | Never finaled issued Sep 2019, no final | 730 Stanyan St | Buhler Commercial | to demolish a 1-story, type 3 restaurant w/ 1 basement.Details
to demolish a 1-story, type 3 restaurant w/ 1 basement. | $250,000 |
| Mar 8, 2018 | Never finaled issued Mar 2018, no final | 730 Stanyan St | Elk Grove Builders Inc | replace (e) roof tiles with new single mansard roof shingles also remode mcdonalds logo on (e) facadeDetails
replace (e) roof tiles with new single mansard roof shingles also remode mcdonalds logo on (e) facade | $20,000 |
| Jul 28, 2016 | Never finaled issued Jul 2016, no final | 730 Stanyan St | street spaceDetails
street space | ||
| Aug 4, 2008 | Never finaled issued Aug 2008, no final | 700 Stanyan St | street space permitDetails
street space permit | ||
| Jul 8, 2008 | Never finaled issued Jul 2008, no final | 700 Stanyan St | street space & sidewalk repairDetails
street space & sidewalk repair | ||
| Dec 8, 2003 | Never finaled issued Dec 2003, no final | 700 Stanyan St | street space and sidewalk repairDetails
street space and sidewalk repair | ||
| Jun 14, 2002 | Never finaled issued Jun 2002, no final | 700 Stanyan St | sidewalk & street space useDetails
sidewalk & street space use | ||
| Jun 10, 2002 | Expired or cancelled expired Oct 2002 | 700 Stanyan St | sidewalk permitDetails
sidewalk permit |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Cahill Hercules Buildeers Joint Venture (5), Cahill Contractors Llc. (4), Buhler Commercial, Elk Grove Builders Inc, Garnett Signs Llc, Rcm Fire Protection Inc.
- Architects
- Yakuh Django Askew (2), Gray Leonard Strang, Ryan Joshua Jang
- Engineers
- Adam French, David Clifton Mar, Jason Ling, Kai Shing Chu, Mario Mendoza
- Authorized agent-otherss
- Leandron Koo
- Lessees
- Attn Yohana Ouiroz Felton Institute
- Subcontractors
- Ramon Misfeldt
Find contractors for work like this
Starts from the last permit filed here; change it to describe your own project. Results cover every building: the city does not class this parcel as single-family, two-family or apartments.