Block 0976, lot 001
2901 Pacific Ave
- City’s use
- Commercial Hotel
- Built
- 1907
- Stories
- 4
- Units
- 1
- Rooms
- 32 bathrooms
- Building
- 28,000 sq ft
- Lot
- 7,496 sq ft
- Zoning
- RM2
- Construction type
- D
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
23 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Dec 14, 2022 | Never finaled issued Apr 2023, no final | 2901 Pacific Av | box out lobby wall to create seating nook at reception desk at entry level, 20 sq. ft. infillDetails
box out lobby wall to create seating nook at reception desk at entry level, 20 sq. ft. infill | $60,000 | |
| Dec 14, 2022 | Never finaled issued Dec 2022, no final | 2901 Pacific Av | Phollies Inc | convert e hotel room to sitting room, living room. remove toilet room, convert to storageDetails
convert e hotel room to sitting room, living room. remove toilet room, convert to storage | $75,000 |
| Oct 26, 2017 | Completed final sign-off Apr 2018 | 2901 Pacific Av | Sarris Construction | replace 117 double hung windows & awning sash pairs with marvin aluminum clad wood double hung inserts with ogee lugs. u-factor = 0.30. windows are visible from street.Details
replace 117 double hung windows & awning sash pairs with marvin aluminum clad wood double hung inserts with ogee lugs. u-factor = 0.30. windows are visible from street. | $150,000 |
| Jun 23, 2017 | Completed final sign-off Jul 2017 | 2901 Pacific Av | Battalion One Fire Protection | as built fire alarm for pa#201612306293Details
as built fire alarm for pa#201612306293 | |
| Mar 22, 2017 | Never finaled issued Jun 2017, no final | 2901 Pacific Av | street spaceDetails
street space | ||
| Feb 16, 2017 | Completed final sign-off Jul 2017 | 2901 Pacific Av | Sarris Construction | replace 50 double awning and double hung sash pairs with marvin aluminum clad wood double hung inserts with ogee lugs placed in alignment with face and inner edge of vertical framing element. these windows are visible from street, u-factor = 0.32Details
replace 50 double awning and double hung sash pairs with marvin aluminum clad wood double hung inserts with ogee lugs placed in alignment with face and inner edge of vertical framing element. these windows are visible from street, u-factor = 0.32 | $45,000 |
| Feb 6, 2017 | Completed final sign-off Jul 2017 | 2901 Pacific Av | Madden Plumbing, Llc | various floors: relocate and change out 43 new heads below new drop ceiling in all bathrooms per nfpa#13 t.i. app 2016-0819-5579Details
various floors: relocate and change out 43 new heads below new drop ceiling in all bathrooms per nfpa#13 t.i. app 2016-0819-5579 | $8,000 |
| Feb 6, 2017 | Expired or cancelled withdrawn Feb 2017 | 2901 Pacific Av | Phollies Inc | title 24: electrical t.i. only: ref pa201608195579. replace and/or repair electrical throughout the building.Details
title 24: electrical t.i. only: ref pa201608195579. replace and/or repair electrical throughout the building. | $1,000 |
| Jan 13, 2017 | Completed final sign-off Jul 2017 | 2901 Pacific Av | Phollies Inc | structural only: revision to pa 2016-0819-5579 additional interior structural support due to field conditions. add structural support to roof framing for mechanical equipmentDetails
structural only: revision to pa 2016-0819-5579 additional interior structural support due to field conditions. add structural support to roof framing for mechanical equipment | $75,000 |
| Dec 30, 2016 | Completed final sign-off Jul 2017 | 2901 Pacific Av | Battalion One Fire Protection | new fire alarm system with new control panel, pull station near panel, readio comminicator, 2 power supply panels, lf sounders in every rm, install monitor modules to tie in to waterflow and tamper switches and relay modules for elev recall ti 201608195579Details
new fire alarm system with new control panel, pull station near panel, readio comminicator, 2 power supply panels, lf sounders in every rm, install monitor modules to tie in to waterflow and tamper switches and relay modules for elev recall ti 201608195579 | $45,000 |
| Dec 30, 2016 | Completed final sign-off Jul 2017 | 2901 Pacific Av | Phollies Inc | revision to 201608195579 mechanical & electrical upgrade to coincide with ti. fire alram & sprinklers on sep permitDetails
revision to 201608195579 mechanical & electrical upgrade to coincide with ti. fire alram & sprinklers on sep permit | $125,000 |
| Nov 15, 2016 | Never finaled issued Nov 2016, no final | 2901 Pacific Av | street spaceDetails
street space | ||
| Aug 19, 2016 | Completed final sign-off Jul 2017 | 2901 Pacific Av | Phollies Inc | project consists of interior upgrades to (e) guestrooms & common areas & upgrades to the (e) elevator. ada upgrades. no exterior work. fire sprinkler under a separate permit. mep under a separate permit.Details
project consists of interior upgrades to (e) guestrooms & common areas & upgrades to the (e) elevator. ada upgrades. no exterior work. fire sprinkler under a separate permit. mep under a separate permit. | $2,900,000 |
| May 19, 2015 | Completed final sign-off Jul 2015 | 2901 Pacific Av | Anderson Roofing & Sheet Metal | reroofingDetails
reroofing | $97,000 |
| Jun 1, 2012 | Completed final sign-off Aug 2012 | 2901 Pacific Av | Faubel Construction Inc. | 1st floor/suite #103 & 109-barrier removal work, alter (e) hotel bathrooms for accessiblityDetails
1st floor/suite #103 & 109-barrier removal work, alter (e) hotel bathrooms for accessiblity | $30,000 |
| Feb 13, 2009 | Completed final sign-off Feb 2009 | 2901 Pacific Av | International Fire Equip | to obtain final inspection for work approved under pa 200603237335, all work has been completedDetails
to obtain final inspection for work approved under pa 200603237335, all work has been completed | |
| Feb 13, 2009 | Completed final sign-off Feb 2009 | 2901 Pacific Av | International Fire Equip | to obtain final inspection for work approved uner pa 200604138850; all work has been completedDetails
to obtain final inspection for work approved uner pa 200604138850; all work has been completed | |
| Dec 18, 2008 | Never finaled issued Dec 2008, no final | 2901 Pacific Av | Simplex Grinnell | add dry pendent fire sprinkler at extg walk in cooler and one each fire sprinkler in storage roomDetails
add dry pendent fire sprinkler at extg walk in cooler and one each fire sprinkler in storage room | $1,540 |
| Apr 13, 2006 | Expired or cancelled expired Feb 2009 | 2901 Pacific Av | International Fire Equip | revision 200603237335 plug & sprinkler outlets & install 3 branch lines with total 5 sprinklers in kitchen.Details
revision 200603237335 plug & sprinkler outlets & install 3 branch lines with total 5 sprinklers in kitchen. | $900 |
| Mar 23, 2006 | Expired or cancelled expired Feb 2009 | 2901 Pacific Av | International Fire Equip | drop down 3" on 4 heads and add one sidewall sprinkler, replace 4 existing pendant heads with new headsDetails
drop down 3" on 4 heads and add one sidewall sprinkler, replace 4 existing pendant heads with new heads | $900 |
| Jan 17, 2006 | Completed final sign-off Jun 2006 | 2901 Pacific Av | Fms Projects Inc. | sprinkler system revisions under separate application. install finish surfaces including sheetrock, cabinets, connectors, lighting, new concrete floor, t-bar ceiling, sink, and warmer oven for hospitalilty rm, please reference structure permit 1074738Details
sprinkler system revisions under separate application. install finish surfaces including sheetrock, cabinets, connectors, lighting, new concrete floor, t-bar ceiling, sink, and warmer oven for hospitalilty rm, please reference structure permit 1074738 | $10,000 |
| Nov 16, 2005 | Completed final sign-off Feb 2006 | 2901 Pacific Av | demo and temporary shoring for hotel. please refer to structural permit 200511107892.Details
demo and temporary shoring for hotel. please refer to structural permit 200511107892. | $5,000 | |
| Nov 10, 2005 | Completed final sign-off Jun 2006 | 2901 Pacific Av | Fms Projects Inc. | structural reinforcement of deteriorted brick foundation. reinforcement of floor joists, construction of framed wall. (floor dining level/0)Details
structural reinforcement of deteriorted brick foundation. reinforcement of floor joists, construction of framed wall. (floor dining level/0) | $25,000 |
Find contractors for work like this